CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
ANR Pipeline Company 1mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
10/23/2024 2:02 pm
Notice Effective Date/Time
11/05/2024 9:00 am
Notice End Date/Time
11/08/2024 8:59 am
Notice ID
12056
Notice Status Desc
Initiate
Prior Notice
Reqrd Rsp
5
Rsp Date/Time
Subject
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
Notice Text
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
ANR has planned maintenance at the Brownsville Compressor Station on the Southeast Mainline. As a result, capacity will be reduced as follows:
11/5 - 11/7 - Brownsville Southbound (LOC #1260569): 239 MMcf/d (leaving 1024 MMcf/d)
ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
13% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Non-Force Majeure Average Usage Quantity pursuant to Section 6.36.2(b) of the Tariff.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
10/23/2024 2:02 pm
Notice Effective Date/Time
11/05/2024 9:00 am
Notice End Date/Time
11/08/2024 8:59 am
Notice ID
12056
Notice Status Desc
Initiate
Prior Notice
Reqrd Rsp
5
Rsp Date/Time
Subject
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
Notice Text
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
ANR has planned maintenance at the Brownsville Compressor Station on the Southeast Mainline. As a result, capacity will be reduced as follows:
11/5 - 11/7 - Brownsville Southbound (LOC #1260569): 239 MMcf/d (leaving 1024 MMcf/d)
ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
13% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Non-Force Majeure Average Usage Quantity pursuant to Section 6.36.2(b) of the Tariff.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
TSP
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
10/23/2024 2:02 pm
Notice Effective Date/Time
11/05/2024 9:00 am
Notice End Date/Time
11/08/2024 8:59 am
Notice ID
12056
Notice Status Desc
Initiate
Prior Notice
Reqrd Rsp
5
Rsp Date/Time
Subject
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
Notice Text
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
ANR has planned maintenance at the Brownsville Compressor Station on the Southeast Mainline. As a result, capacity will be reduced as follows:
11/5 - 11/7 - Brownsville Southbound (LOC #1260569): 239 MMcf/d (leaving 1024 MMcf/d)
ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
13% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Non-Force Majeure Average Usage Quantity pursuant to Section 6.36.2(b) of the Tariff.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267
006958581
TSP Name
ANR Pipeline Company
Notice Type Desc
Plnd Outage
Posting Date/Time
10/23/2024 2:02 pm
Notice Effective Date/Time
11/05/2024 9:00 am
Notice End Date/Time
11/08/2024 8:59 am
Notice ID
12056
Notice Status Desc
Initiate
Prior Notice
Reqrd Rsp
5
Rsp Date/Time
Subject
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
Notice Text
CAPACITY REDUCTION - Southeast Mainline - Brownsville Southbound (Posted: 10/23/24)
ANR has planned maintenance at the Brownsville Compressor Station on the Southeast Mainline. As a result, capacity will be reduced as follows:
11/5 - 11/7 - Brownsville Southbound (LOC #1260569): 239 MMcf/d (leaving 1024 MMcf/d)
ANR anticipates this posting may result in Firm Primary, Firm Secondary and Interruptible curtailments. Estimated impact to Firm Primary as follows:
0% - Based on the Current Net Shipper Nominations
13% - Based on the Current Contracted MDQ
Any reservation charge credits (RCCs) will be determined per the process set forth in the General Terms and Conditions, Section 6.36 of ANR's FERC Gas Tariff ("Tariff"). However, ANR will only issue RCCs if ANR is unable to schedule or deliver primary firm nominated capacity as a result of the outage. In the event RCCs are issued as set forth in the Tariff, shippers will receive RCCs based on its 7-day Non-Force Majeure Average Usage Quantity, as defined in Section 6.36.2 of ANR's Tariff, less any scheduled quantities on the contract. By means of this notice, ANR is establishing which specific Gas Days will be included when determining a shipper's 7-day Non-Force Majeure Average Usage Quantity pursuant to Section 6.36.2(b) of the Tariff.
Please direct any questions to your Account Coordinator, Customer Service Representative, or the Nominations and Scheduling hotline @ 800-827-5267