Gulf Coast Express Pipeline Icon

Extended: GCX Inspections & ESD Testing

Gulf Coast Express Pipeline 2w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  81252229-GULF COAST EXPRESS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  11/03/2024 12:49:07PM Notice End Date/Time:  11/04/2024 9:00:00am
Post Date/Time:  11/3/2024 12:49:07 PM Notice ID: 203700
Reqrd Rsp:  5 Rsp Date: 
Notice Stat Desc:  SUPERSEDE Prior Notice:  203698
Subject:  Extended: GCX Inspections & ESD Testing
Notice Text:

Extended: GCX Inspections & ESD Testing

The previously posted GCX maintenance has been extended through the Gas Day of Sunday, November 3, 2024. Total Mainline capacity on GCX will remain at the reduced capacity of 1,630,000 MMBtu.

Should you have any questions, please contact your GCX Account Representative.

 

 

Reminder: GCX Inspections & ESD Testing

As a reminder, beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.

 

 

Previously Posted on 9/23/24

Beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.

 

TSP/TSP Name:  81252229-GULF COAST EXPRESS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  11/03/2024 12:49:07PM Notice End Date/Time:  11/04/2024 9:00:00am
Post Date/Time:  11/3/2024 12:49:07 PM Notice ID: 203700
Reqrd Rsp:  5 Rsp Date: 
Notice Stat Desc:  SUPERSEDE Prior Notice:  203698
Subject:  Extended: GCX Inspections & ESD Testing
Notice Text:

Extended: GCX Inspections & ESD Testing

The previously posted GCX maintenance has been extended through the Gas Day of Sunday, November 3, 2024. Total Mainline capacity on GCX will remain at the reduced capacity of 1,630,000 MMBtu.

Should you have any questions, please contact your GCX Account Representative.

 

 

Reminder: GCX Inspections & ESD Testing

As a reminder, beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.

 

 

Previously Posted on 9/23/24

Beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.