Heidelberg Compressor Station Maintenance
Gulf South Pipeline 2mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Notice
Critical / Planned Service Outage
TSP:
Post Date/Time:
78444247
09/24/2024 01:39:19PM
Category:
TSP Name: Gulf South Pipeline Company, LLC
Notice Effective Date/Time: 11/18/2024 09:00:00AM
Notice Type Desc: Maintenance
Heidelberg Compressor Station Maintenance
Subject:
Initiate
5035436
Notice Stat Desc:
Prior Notice:
Notice ID:
Response Date/Time:
Reqrd Rsp Desc:
Notice End Date/Time: 11/23/2024 09:00:00 AM
Critical: Y
No response required
Gulf South is preforming at Heidelberg Compressor Station.
Loc 23373 (Transco (Petal Pipeline)) - Receipt capacity will be limited to 125,000 dth. This maintenance
has the potential to impact all services, including Primary Firm Service.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.
Notice Text:
09/24/2024 1:39:53PM
Page 1 of 1
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical / Planned Service Outage
Post Date/Time: 09/24/2024 01:39:19PM
Notice Type Desc: Maintenance
Notice Effective Date/Time: 11/18/2024 09:00:00AM
Notice Stat Desc: Initiate
Notice End Date/Time: 11/23/2024 09:00:00 AM
Notice ID: 5035436
Response Date/Time:
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No response required
Subject: Heidelberg Compressor Station Maintenance
Notice Text:
Gulf South is preforming at Heidelberg Compressor Station.
Loc 23373 (Transco (Petal Pipeline)) - Receipt capacity will be limited to 125,000 dth. This maintenance
has the potential to impact all services, including Primary Firm Service.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.
09/24/2024 1:39:53PM
Page 1 of 1