Line N12 Outage: Summer 2025 - Revision 1
National Fuel Gas Supply 19h ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: National Fuel Gas Supply Corporation - Critical Notice
TSP: 007912959
Post Date: 4/28/2025
Post Time: 10:13:00AM CCT
Notice Type: Planned Service Outage, Scheduling Alert
Reqrd Rsp: 5
Critical: Y
Notice ID: 1160330
Notice Status: 2
Notice Eff Date/Time: 4/28/2025 10:15:00AM CCT
Notice End Date/Time: 5/28/2025 09:00:00AM CCT
Superseded System Notice ID: 1145171
Subject: Line N12 Outage: Summer 2025 - Revision 1
Notice Text
Line N12 Outage: Summer 2025 - Revision 1
Line N12 construction has been postponed until further notice. No outages will occur in 2025.
Updates will be provided as available.
********** Prior Notice Below **********
Line N12 Outage: Summer 2025
Line N12 will undergo construction beginning 6/1/2025 through 9/15/2025.
Deliveries to Peoples Natural Gas at meter PSN1300631 (from line N12) will be unavailable for the duration of this work.
All gas will be fed at meter PSN1322481 (from line SM14).
Additionally, due to this outage, the following production meters will be shut-in:
PSP1U44931 – Pin Oak Energy Partners, LLC.
PSP1246761 – Three Dog Energy, LLC.
Updates will be provided as available.
TSP Name: National Fuel Gas Supply Corporation - Critical Notice
TSP: 007912959
Post Date: 4/28/2025
Post Time: 10:13:00AM CCT
Notice Type: Planned Service Outage, Scheduling Alert
Reqrd Rsp: 5
Critical: Y
Notice ID: 1160330
Notice Status: 2
Notice Eff Date/Time: 4/28/2025 10:15:00AM CCT
Notice End Date/Time: 5/28/2025 09:00:00AM CCT
Superseded System Notice ID: 1145171
Subject: Line N12 Outage: Summer 2025 - Revision 1
Notice Text
Line N12 Outage: Summer 2025 - Revision 1
Line N12 construction has been postponed until further notice. No outages will occur in 2025.
Updates will be provided as available.
********** Prior Notice Below **********
Line N12 Outage: Summer 2025
Line N12 will undergo construction beginning 6/1/2025 through 9/15/2025.
Deliveries to Peoples Natural Gas at meter PSN1300631 (from line N12) will be unavailable for the duration of this work.
All gas will be fed at meter PSN1322481 (from line SM14).
Additionally, due to this outage, the following production meters will be shut-in:
PSP1U44931 – Pin Oak Energy Partners, LLC.
PSP1246761 – Three Dog Energy, LLC.
Updates will be provided as available.