Blue Lake Pipe Replacement & Portland Hydro Test - Maintenance Complete
Northwest 3mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 08/18/2024 11:54 AM MCT
Notice Eff D/T: 08/18/2024 11:54 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-123
Prior Notice: 24-118
Subject: Blue Lake Pipe Replacement & Portland Hydro Test - Maintenance Complete
Notice Text:
Northwest Pipeline would like to inform its customers that
the Blue Lake Pipe Replacement and Portland Hydro Test (Gorge
Outage) posted on Northwest’s website from Gas Day August 02,
2024, through Gas Day August 18, 2024, and referenced in Notice
#24-118 has now been completed.
Northwest will begin accepting nominations up to the design of
540,000 Dth/d northbound through the Willard CS and nominations
up to the design of 407,000 Dth/d southbound through the
Washougal South Constraint effective for the ID2 cycle for Gas
Day August 18, 2024.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 08/18/2024 11:54 AM MCT
Notice Eff D/T: 08/18/2024 11:54 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-123
Prior Notice: 24-118
Subject: Blue Lake Pipe Replacement & Portland Hydro Test - Maintenance Complete
Notice Text:
Northwest Pipeline would like to inform its customers that
the Blue Lake Pipe Replacement and Portland Hydro Test (Gorge
Outage) posted on Northwest’s website from Gas Day August 02,
2024, through Gas Day August 18, 2024, and referenced in Notice
#24-118 has now been completed.
Northwest will begin accepting nominations up to the design of
540,000 Dth/d northbound through the Willard CS and nominations
up to the design of 407,000 Dth/d southbound through the
Washougal South Constraint effective for the ID2 cycle for Gas
Day August 18, 2024.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
TSP Name: Northwest Pipeline LLC TSP: 67977322
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 08/18/2024 11:54 AM MCT
Notice Eff D/T: 08/18/2024 11:54 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-123
Prior Notice: 24-118
Subject: Blue Lake Pipe Replacement & Portland Hydro Test - Maintenance Complete
Notice Text:
Northwest Pipeline would like to inform its customers that
the Blue Lake Pipe Replacement and Portland Hydro Test (Gorge
Outage) posted on Northwest’s website from Gas Day August 02,
2024, through Gas Day August 18, 2024, and referenced in Notice
#24-118 has now been completed.
Northwest will begin accepting nominations up to the design of
540,000 Dth/d northbound through the Willard CS and nominations
up to the design of 407,000 Dth/d southbound through the
Washougal South Constraint effective for the ID2 cycle for Gas
Day August 18, 2024.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.
Critical: Y
Notice Stat Desc: SUPERSEDE
Notice Type Desc: MAINTENANCE
Post D/T: 08/18/2024 11:54 AM MCT
Notice Eff D/T: 08/18/2024 11:54 AM MCT
Notice End D/T:
Reqrd Rsp Desc: No response required
Rsp D/T:
Notice ID: 24-123
Prior Notice: 24-118
Subject: Blue Lake Pipe Replacement & Portland Hydro Test - Maintenance Complete
Notice Text:
Northwest Pipeline would like to inform its customers that
the Blue Lake Pipe Replacement and Portland Hydro Test (Gorge
Outage) posted on Northwest’s website from Gas Day August 02,
2024, through Gas Day August 18, 2024, and referenced in Notice
#24-118 has now been completed.
Northwest will begin accepting nominations up to the design of
540,000 Dth/d northbound through the Willard CS and nominations
up to the design of 407,000 Dth/d southbound through the
Washougal South Constraint effective for the ID2 cycle for Gas
Day August 18, 2024.
Please reference the Maintenance Schedule tab at
www.northwest.williams.com for more information.
If you have any questions, please call your Commercial Services
Representative or the hotline at 713-215-6301.