Update#2 Schd Maint Holy Trinity Seg 655
Southern Natural Gas 1mo ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 6900518-SOUTHERN NATURAL GAS CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 10/09/2024 11:37:49AM | Notice End Date/Time: 10/10/2024 9:00:00am |
Post Date/Time: 10/9/2024 11:37:49 AM | Notice ID: 709910 |
Reqrd Rsp: 1 | Rsp Date: 10/09/2024 |
Notice Stat Desc: SUPERSEDE | Prior Notice: 709890 |
Subject: Update#2 Schd Maint Holy Trinity Seg 655 |
Scheduled Pipeline Maintenance – Holy Trinity compressor station (Segment 655) – Update #2
As previously referenced in posting (#709890) and Southern's weekly EBB postings, the pipeline maintenance at the Holy Trinity compressor station (Segment 655) scheduled from gas day, Wednesday, October 9th, 2024, to gas day, Saturday October 12th, 2024, has been rescheduled to gas day, Monday October 14th, 2024, to gas day, Friday October 18th, 2024. As a result, Holy Trinity (Segment 655) capacity of 127,000Dth/d will be restored to full capacity effective ID1 cycle, gas day Wednesday October 9th, 2024.
Starting Monday October 14th, Holy Trinity (Segment 655) capacity of 127,000Dth/d will be reduced by 37,000Dth/d to 90,000Dth/d through gas day, Friday October 18th, 2024.
Please call your Account Manager or Scheduling Representative if you have questions.
SNG Gas Control
TSP/TSP Name: 6900518-SOUTHERN NATURAL GAS CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 10/09/2024 11:37:49AM | Notice End Date/Time: 10/10/2024 9:00:00am |
Post Date/Time: 10/9/2024 11:37:49 AM | Notice ID: 709910 |
Reqrd Rsp: 1 | Rsp Date: 10/09/2024 |
Notice Stat Desc: SUPERSEDE | Prior Notice: 709890 |
Subject: Update#2 Schd Maint Holy Trinity Seg 655 |
Scheduled Pipeline Maintenance – Holy Trinity compressor station (Segment 655) – Update #2
As previously referenced in posting (#709890) and Southern's weekly EBB postings, the pipeline maintenance at the Holy Trinity compressor station (Segment 655) scheduled from gas day, Wednesday, October 9th, 2024, to gas day, Saturday October 12th, 2024, has been rescheduled to gas day, Monday October 14th, 2024, to gas day, Friday October 18th, 2024. As a result, Holy Trinity (Segment 655) capacity of 127,000Dth/d will be restored to full capacity effective ID1 cycle, gas day Wednesday October 9th, 2024.
Starting Monday October 14th, Holy Trinity (Segment 655) capacity of 127,000Dth/d will be reduced by 37,000Dth/d to 90,000Dth/d through gas day, Friday October 18th, 2024.
Please call your Account Manager or Scheduling Representative if you have questions.
SNG Gas Control