Tennessee Gas Pipeline Icon

RESTRICTIONS FOR 10-21-2024 ID2

Tennessee Gas Pipeline 1mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  10/21/2024 3:35:00PM Notice End Date/Time:  10/22/2024 9:00:00am
Post Date/Time:  10/21/2024 3:35:00 PM Notice ID: 392609
Reqrd Rsp:  1 Rsp Date:  10/21/2024
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 10-21-2024 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of Monday, October 21, 2024 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR UNDER-TAKES OUT OF THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

METER RESTRICTIONS

·         LOBO/TGP King Ranch Jim Wells Receipt Meter (Pin 412400) - through 100% of PIP increases due to operational concerns; 901 Dths

·         WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through 100% of SOP increases due to operational concerns; 130,487 Dths

·         VCP/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through 100% of SOP increases due to operational concerns; 39,863 Dths

·         NMP/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SA increases due to operational concerns; 45,000 Dths

·         ETP/TGP Shoup Nueces Receipt Meter (Pin 412669) - through 100% of SA increases due to operational concerns; 471 Dths

·         ENTRPRSE/TGP Agua Dulce Nueces Receipt Meter (Pin 411306) - through 100% of SA increases due to operational concerns; 106 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 99,604 Dths

·         STA 860 South 800 Line (Segment 847 BH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 1,107 Dths

·         STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 2,306 Dths

·         STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP increases due to operational concerns; 10,000 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases due to operational concerns; 9,965 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 254,182 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 140,155 Dths

·         STA 315 (Segment 315 BH) - through approx 59% of SOP increases due to nominations in excess of operational capacity; 194,872 Dths

·         Z5hc North (Segment 299 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 125,492 Dths

·         STA 245 (Segment 245 FH) - through approx 49% of SOP increases due to nominations in excess of operational capacity; 87,011 Dths

·         STA 249 (Segment 249 FH) - through approx 17% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 11,955 Dths

·         MLV 273 (Segment 284 FH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 78,428 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

 

Tennessee will not accept nominations for FSAO injections at all storage fields.

 

Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  10/21/2024 3:35:00PM Notice End Date/Time:  10/22/2024 9:00:00am
Post Date/Time:  10/21/2024 3:35:00 PM Notice ID: 392609
Reqrd Rsp:  1 Rsp Date:  10/21/2024
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 10-21-2024 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of Monday, October 21, 2024 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR UNDER-TAKES OUT OF THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

METER RESTRICTIONS

·         LOBO/TGP King Ranch Jim Wells Receipt Meter (Pin 412400) - through 100% of PIP increases due to operational concerns; 901 Dths

·         WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through 100% of SOP increases due to operational concerns; 130,487 Dths

·         VCP/TGP Valley Crossing Allocation Receipt Meter (Pin 53608) - through 100% of SOP increases due to operational concerns; 39,863 Dths

·         NMP/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SA increases due to operational concerns; 45,000 Dths

·         ETP/TGP Shoup Nueces Receipt Meter (Pin 412669) - through 100% of SA increases due to operational concerns; 471 Dths

·         ENTRPRSE/TGP Agua Dulce Nueces Receipt Meter (Pin 411306) - through 100% of SA increases due to operational concerns; 106 Dths

SEGMENT RESTRICTIONS

·         STA 1 (Segment 101 BH) - through 100% of SOP increases due to operational concerns; 99,604 Dths

·         STA 860 South 800 Line (Segment 847 BH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 1,107 Dths

·         STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 2,306 Dths

·         STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP increases due to operational concerns; 10,000 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases due to operational concerns; 9,965 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 254,182 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 140,155 Dths

·         STA 315 (Segment 315 BH) - through approx 59% of SOP increases due to nominations in excess of operational capacity; 194,872 Dths

·         Z5hc North (Segment 299 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 125,492 Dths

·         STA 245 (Segment 245 FH) - through approx 49% of SOP increases due to nominations in excess of operational capacity; 87,011 Dths

·         STA 249 (Segment 249 FH) - through approx 17% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 11,955 Dths

·         MLV 273 (Segment 284 FH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 78,428 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

 

Tennessee will not accept nominations for FSAO injections at all storage fields.

 

Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.