RESTRICTIONS FOR 03-09-2025 TIMELY CYCLE
Tennessee Gas Pipeline 17h ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 03/08/2025 3:06:56PM | Notice End Date/Time: 03/09/2025 9:00:00am |
Post Date/Time: 3/8/2025 3:06:56 PM | Notice ID: 393963 |
Reqrd Rsp: 1 | Rsp Date: 03/08/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 03-09-2025 TIMELY CYCLE |
Effective Timely Cycle (9:00) for the gas day of Sunday, March 09, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY (SEGMENTS 527, 529, 530, 534, 539, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 40,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 59% of SOP due to operational concerns; 69,875 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 83% of SIPss due to nominations in excess of operational capacity; 140,493 Dths
· IROQUOIS/TGP Shelton Interconnect F Receipt Meter (Pin 412180) - through approx 84% of IT due to nominations in excess of operational capacity; 50,058 Dths
· Wright Receipt Meter (Pin 412181) - through approx 65% of SOP due to nominations in excess of operational capacity; 65,834 Dths
SEGMENT RESTRICTIONS
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to emergent repair at STA 40; 10,664 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP due to nominations in excess of operational capacity; 5,146 Dths
· STA 307 (Segment 307 BH) - through approx 38% of SOP due to nominations in excess of operational capacity; 100,416 Dths
· MLV 314 East (Segment 314 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 222,475 Dths
· STA 315 (Segment 315 BH) - through approx 63% of SOP due to nominations in excess of operational capacity; 257,373 Dths
· STA 321 (Segment 321 FH) - through approx 76% of SOP due to emergent repair at STA 321 Unit 5B; 709,472 Dths
· STA 325 (Segment 324 FH) - through approx 27% of SOP due to nominations in excess of operational capacity; 86,585 Dths
· MLV 330 (Segment 324 FH) - through approx 44% of SOP due to nominations in excess of operational capacity; 184,914 Dths
· MLV 336 East (Segment 336 FH) - through approx 94% of SOP due to nominations in excess of operational capacity; 81,553 Dths
· STA 224 (Segment 224 FH) - through approx 61% of SOP due to nominations in excess of operational capacity; 153,253 Dths
· Z5hc North (Segment 299 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 791,905 Dths
· STA 237 East Of Z5w Pool (Segment 237 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 266,146 Dths
· STA 245 (Segment 245 FH) - through approx 91% of SOP due to nominations in excess of operational capacity; 436,527 Dths
· STA 249 (Segment 249 FH) - through approx 72% of SOP due to nominations in excess of operational capacity; 194,374 Dths
· STA 254 (Segment 249 FH) - through approx 15% of SOP due to nominations in excess of operational capacity; 99,768 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 55% of SOP due to nominations in excess of operational capacity; 104,736 Dths
· MLV 273 (Segment 284 FH) - through approx 87% of SOP due to nominations in excess of operational capacity; 211,504 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Nominations for Authorized Overrun Withdrawal Services (FS-AO) at the Northern MA (460018) storage field, the Portland MA (460025) storage field, the Portland PA (460020) storage field or the Bear Creek PA (460017) storage field will not be allowed until further notice. Additionally, customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) only until further notice.
Nominations for Firm Storage Flex Authorized Overrun (FSF-AO) Withdrawal Services under Rate Schedule FS-F at the Pine Prairie Virtual Meter (54628) will not be allowed until further notice.
Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals. Additionally, no transfers from IS-MA and IS-PA to FS will be allowed until further notice.
No Loans or Park Withdrawals under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 03/08/2025 3:06:56PM | Notice End Date/Time: 03/09/2025 9:00:00am |
Post Date/Time: 3/8/2025 3:06:56 PM | Notice ID: 393963 |
Reqrd Rsp: 1 | Rsp Date: 03/08/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 03-09-2025 TIMELY CYCLE |
Effective Timely Cycle (9:00) for the gas day of Sunday, March 09, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY (SEGMENTS 527, 529, 530, 534, 539, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 40,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 59% of SOP due to operational concerns; 69,875 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 83% of SIPss due to nominations in excess of operational capacity; 140,493 Dths
· IROQUOIS/TGP Shelton Interconnect F Receipt Meter (Pin 412180) - through approx 84% of IT due to nominations in excess of operational capacity; 50,058 Dths
· Wright Receipt Meter (Pin 412181) - through approx 65% of SOP due to nominations in excess of operational capacity; 65,834 Dths
SEGMENT RESTRICTIONS
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to emergent repair at STA 40; 10,664 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP due to nominations in excess of operational capacity; 5,146 Dths
· STA 307 (Segment 307 BH) - through approx 38% of SOP due to nominations in excess of operational capacity; 100,416 Dths
· MLV 314 East (Segment 314 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 222,475 Dths
· STA 315 (Segment 315 BH) - through approx 63% of SOP due to nominations in excess of operational capacity; 257,373 Dths
· STA 321 (Segment 321 FH) - through approx 76% of SOP due to emergent repair at STA 321 Unit 5B; 709,472 Dths
· STA 325 (Segment 324 FH) - through approx 27% of SOP due to nominations in excess of operational capacity; 86,585 Dths
· MLV 330 (Segment 324 FH) - through approx 44% of SOP due to nominations in excess of operational capacity; 184,914 Dths
· MLV 336 East (Segment 336 FH) - through approx 94% of SOP due to nominations in excess of operational capacity; 81,553 Dths
· STA 224 (Segment 224 FH) - through approx 61% of SOP due to nominations in excess of operational capacity; 153,253 Dths
· Z5hc North (Segment 299 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 791,905 Dths
· STA 237 East Of Z5w Pool (Segment 237 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 266,146 Dths
· STA 245 (Segment 245 FH) - through approx 91% of SOP due to nominations in excess of operational capacity; 436,527 Dths
· STA 249 (Segment 249 FH) - through approx 72% of SOP due to nominations in excess of operational capacity; 194,374 Dths
· STA 254 (Segment 249 FH) - through approx 15% of SOP due to nominations in excess of operational capacity; 99,768 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 55% of SOP due to nominations in excess of operational capacity; 104,736 Dths
· MLV 273 (Segment 284 FH) - through approx 87% of SOP due to nominations in excess of operational capacity; 211,504 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Nominations for Authorized Overrun Withdrawal Services (FS-AO) at the Northern MA (460018) storage field, the Portland MA (460025) storage field, the Portland PA (460020) storage field or the Bear Creek PA (460017) storage field will not be allowed until further notice. Additionally, customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) only until further notice.
Nominations for Firm Storage Flex Authorized Overrun (FSF-AO) Withdrawal Services under Rate Schedule FS-F at the Pine Prairie Virtual Meter (54628) will not be allowed until further notice.
Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals. Additionally, no transfers from IS-MA and IS-PA to FS will be allowed until further notice.
No Loans or Park Withdrawals under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.