Tennessee Gas Pipeline Icon

RESTRICTIONS FOR 04-03-2025 ID1

Tennessee Gas Pipeline 2w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/03/2025 11:30:32AM Notice End Date/Time:  04/04/2025 9:00:00am
Post Date/Time:  4/3/2025 11:30:32 AM Notice ID: 394213
Reqrd Rsp:  1 Rsp Date:  04/03/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-03-2025 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Thursday, April 03, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 43,863 Dths

·         GULFSTH/TGP Worthy Road South Ouach Delivery Meter (Pin 49780) - through 100% of SIPps increases due to operational concerns; 5,000 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 12,749 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of SIPss increases due to nominations in excess of operational capacity; 25,344 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,664 Dths

·         STA 834 (Segment 834 BH) - through 100% of IT increases due to scheduled maintenance and nominations in excess of operational capacity; 989 Dths

·         STA 860 South 500 Line (Segment 548 BH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 3,139 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 421,706 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 281,825 Dths

·         STA 315 (Segment 315 BH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 424,680 Dths

·         STA 321 (Segment 321 FH) - through approx 98% of SOP increases due to emergent repair at STA 321 Unit 5B; 305,923 Dths

·         Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 312,713 Dths

·         STA 237 East Of Z5w Pool (Segment 237 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 348,806 Dths

·         STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 332,831 Dths

·         STA 249 (Segment 249 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 180,033 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 194,812 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/03/2025 11:30:32AM Notice End Date/Time:  04/04/2025 9:00:00am
Post Date/Time:  4/3/2025 11:30:32 AM Notice ID: 394213
Reqrd Rsp:  1 Rsp Date:  04/03/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-03-2025 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Thursday, April 03, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 43,863 Dths

·         GULFSTH/TGP Worthy Road South Ouach Delivery Meter (Pin 49780) - through 100% of SIPps increases due to operational concerns; 5,000 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 12,749 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of SIPss increases due to nominations in excess of operational capacity; 25,344 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,664 Dths

·         STA 834 (Segment 834 BH) - through 100% of IT increases due to scheduled maintenance and nominations in excess of operational capacity; 989 Dths

·         STA 860 South 500 Line (Segment 548 BH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 3,139 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 421,706 Dths

·         MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 281,825 Dths

·         STA 315 (Segment 315 BH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 424,680 Dths

·         STA 321 (Segment 321 FH) - through approx 98% of SOP increases due to emergent repair at STA 321 Unit 5B; 305,923 Dths

·         Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 312,713 Dths

·         STA 237 East Of Z5w Pool (Segment 237 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 348,806 Dths

·         STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 332,831 Dths

·         STA 249 (Segment 249 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 180,033 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 194,812 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.