RESTRICTIONS FOR 04-08-2025 ID1
Tennessee Gas Pipeline 1w ago
All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 04/08/2025 11:17:01AM | Notice End Date/Time: 04/09/2025 9:00:00am |
Post Date/Time: 4/8/2025 11:17:01 AM | Notice ID: 394252 |
Reqrd Rsp: 1 | Rsp Date: 04/08/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 04-08-2025 ID1 |
Effective Intraday 1 Cycle (14:00) for the gas day of Tuesday, April 08, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 245 ON THE 200 LINE AND FOR ALL AREAS EAST OF STA 336 ON THE 300 LINE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 32,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 8,000 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of PIP increases due to operational concerns; 95 Dths
· HESS/TGP Ratcliffe: Dip 542B 101.1, Delivery Meter (Pin 421078) - through 100% of SOP receipt increases due to displacement gas unavailable for backhaul; 10,000 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 98% of SIPps increases due to nominations in excess of operational capacity; 88,401 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through approx 35% of PS IT ; 10,395 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,000 Dths
· STA 823 (Segment 823 BH) - through approx 77% of PS IT ; 9,921 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,953 Dths
· STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 18,615 Dths
· STA 114 East (Segment 114 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 5,084 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 423,714 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 460,013 Dths
· STA 315 (Segment 315 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 168,775 Dths
· STA 321 (Segment 321 FH) - through approx 96% of SOP increases due to emergent repair at STA 321 UNIT 5B; 371,934 Dths
· MLV 330 (Segment 324 FH) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 145,979 Dths
· Z5hc North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 381,607 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 462,044 Dths
· STA 249 (Segment 249 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 357,776 Dths
· STA 254 (Segment 249 FH) - through approx 22% of SOP increases due to nominations in excess of operational capacity; 25,920 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 158,627 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 156,192 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 04/08/2025 11:17:01AM | Notice End Date/Time: 04/09/2025 9:00:00am |
Post Date/Time: 4/8/2025 11:17:01 AM | Notice ID: 394252 |
Reqrd Rsp: 1 | Rsp Date: 04/08/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 04-08-2025 ID1 |
Effective Intraday 1 Cycle (14:00) for the gas day of Tuesday, April 08, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 245 ON THE 200 LINE AND FOR ALL AREAS EAST OF STA 336 ON THE 300 LINE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 32,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 8,000 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of PIP increases due to operational concerns; 95 Dths
· HESS/TGP Ratcliffe: Dip 542B 101.1, Delivery Meter (Pin 421078) - through 100% of SOP receipt increases due to displacement gas unavailable for backhaul; 10,000 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 98% of SIPps increases due to nominations in excess of operational capacity; 88,401 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through approx 35% of PS IT ; 10,395 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,000 Dths
· STA 823 (Segment 823 BH) - through approx 77% of PS IT ; 9,921 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,953 Dths
· STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 18,615 Dths
· STA 114 East (Segment 114 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 5,084 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 423,714 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 460,013 Dths
· STA 315 (Segment 315 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 168,775 Dths
· STA 321 (Segment 321 FH) - through approx 96% of SOP increases due to emergent repair at STA 321 UNIT 5B; 371,934 Dths
· MLV 330 (Segment 324 FH) - through approx 88% of SOP increases due to nominations in excess of operational capacity; 145,979 Dths
· Z5hc North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 381,607 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 462,044 Dths
· STA 249 (Segment 249 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 357,776 Dths
· STA 254 (Segment 249 FH) - through approx 22% of SOP increases due to nominations in excess of operational capacity; 25,920 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 158,627 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 156,192 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.