Job #909867 MLC Mississippi River to Sta 65 Planned Outage and Maintenance Summary

Transco 1mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 10/22/2024
Notice Eff Time: 08:33:37 CDT
Notice End Date:
Notice End Time:
Notice ID: 15046806
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 10/22/2024
Post Time: 08:33:37 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job #909867 MLC Mississippi River to Sta 65 Planned Outage and Maintenance Summary

Transco will be performing necessary pipeline inspection maintenance associated with Job #909867 on its 2024 Planned Outage and Maintenance Summary. This maintenance activity may impact the availability of transportation services moving south to north through Compressor Station 60. The current schedule for this maintenance is Nov 4, 2024 to Nov 8, 2024. 

The specific dates that will be impacted are subject to change, but the current schedule is outlined below.  

Cleaner Tool – 11/4 

Smart Tool – 11/8 

During this period of planned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving south to north through the location will not be available.  

Operating Conditions resulting from this work will also require Transco to manage transportation services moving south to north through the TSB location listed below. The total quantity available will be contingent on system conditions during the maintenance period but is anticipated to be limited to the quantity indicated below. Transactions moving north to south through this location will not be impacted. 

The receipt-based Throughput Section Boundary (TSB) at mainline milepost 588.62 (Station 60) will be used to manage capacity availability including any required changes to the expected total quantity available during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of primary-firm transportation services during the indicated period. 

TSB Name - Location  

Location ID  

Flow Direction  

Design Capacity (Mdt/d)  

Total Primary-Firm Qty Available   (Mdt/d) 

% Cuts (Primary)– Potential   Shipper Impact (Based on Historical Utilization) *   

Station 60 MP 588.62 

9000000  

South to North  

2,015 

1,325 

0-5%  

 

*% Cuts (Primary) is an estimate of the impact to primary firm shippers based on historical utilization and anticipated volumes during the time of constraint. These amounts are subject to change based on actual nominated firm volumes and changes in the amount of available capacity 

 

If you have any questions, please contact your Transportation Services Representative.  

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 10/22/2024
Notice Eff Time: 08:33:37 CDT
Notice End Date:
Notice End Time:
Notice ID: 15046806
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 10/22/2024
Post Time: 08:33:37 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job #909867 MLC Mississippi River to Sta 65 Planned Outage and Maintenance Summary

Transco will be performing necessary pipeline inspection maintenance associated with Job #909867 on its 2024 Planned Outage and Maintenance Summary. This maintenance activity may impact the availability of transportation services moving south to north through Compressor Station 60. The current schedule for this maintenance is Nov 4, 2024 to Nov 8, 2024. 

The specific dates that will be impacted are subject to change, but the current schedule is outlined below.  

Cleaner Tool – 11/4 

Smart Tool – 11/8 

During this period of planned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving south to north through the location will not be available.  

Operating Conditions resulting from this work will also require Transco to manage transportation services moving south to north through the TSB location listed below. The total quantity available will be contingent on system conditions during the maintenance period but is anticipated to be limited to the quantity indicated below. Transactions moving north to south through this location will not be impacted. 

The receipt-based Throughput Section Boundary (TSB) at mainline milepost 588.62 (Station 60) will be used to manage capacity availability including any required changes to the expected total quantity available during this planned work. An updated Market and Production Area constraint notice will include the location and the available quantity of primary-firm transportation services during the indicated period. 

TSB Name - Location  

Location ID  

Flow Direction  

Design Capacity (Mdt/d)  

Total Primary-Firm Qty Available   (Mdt/d) 

% Cuts (Primary)– Potential   Shipper Impact (Based on Historical Utilization) *   

Station 60 MP 588.62 

9000000  

South to North  

2,015 

1,325 

0-5%  

 

*% Cuts (Primary) is an estimate of the impact to primary firm shippers based on historical utilization and anticipated volumes during the time of constraint. These amounts are subject to change based on actual nominated firm volumes and changes in the amount of available capacity 

 