Job 113157 Station 77 Eminence Storage Planned Outage and Maintenance Summary

Transco 1mo ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 03/17/2025
Notice Eff Time: 11:48:37 CDT
Notice End Date:
Notice End Time:
Notice ID: 15480534
Notice Stat Desc: Supersede
Notice Type Desc: Maint
Post Date: 03/17/2025
Post Time: 11:48:37 CDT
Prior Notice: 15443875
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job 113157 Station 77 Eminence Storage Planned Outage and Maintenance Summary

Transco will be performing annual spring shut in tests at the Eminence Storage facility, currently scheduled from April 1, 2025 through April 7, 2025 May 5, 2025 through May 9, 2025.

During this period, the Eminence Storage Field will not be available for service to allow for required DOT compliance testing work to be performed. Services under ESS rate schedules may not be available for the period due to Operating Conditions resulting from this planned outage. 

If Transco is required to restrict ESS Injection or withdrawal services, additional notice will be provided.  

Additionally, this work will also reduce system flexibility and recommend all parties maintain a concurrent balance of receipts and deliveries daily.

If you have any questions, please contact your Transportation Services representative.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 03/17/2025
Notice Eff Time: 11:48:37 CDT
Notice End Date:
Notice End Time:
Notice ID: 15480534
Notice Stat Desc: Supersede
Notice Type Desc: Maint
Post Date: 03/17/2025
Post Time: 11:48:37 CDT
Prior Notice: 15443875
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Job 113157 Station 77 Eminence Storage Planned Outage and Maintenance Summary

Transco will be performing annual spring shut in tests at the Eminence Storage facility, currently scheduled from April 1, 2025 through April 7, 2025 May 5, 2025 through May 9, 2025.

During this period, the Eminence Storage Field will not be available for service to allow for required DOT compliance testing work to be performed. Services under ESS rate schedules may not be available for the period due to Operating Conditions resulting from this planned outage. 

If Transco is required to restrict ESS Injection or withdrawal services, additional notice will be provided.  

Additionally, this work will also reduce system flexibility and recommend all parties maintain a concurrent balance of receipts and deliveries daily.

If you have any questions, please contact your Transportation Services representative.