Station 155 Planned Outage and Maintenance Summary

Transco 1w ago

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 04/08/2025
Notice Eff Time: 09:51:37 CDT
Notice End Date:
Notice End Time:
Notice ID: 15551159
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 04/08/2025
Post Time: 09:51:37 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Station 155 Planned Outage and Maintenance Summary

Transco will be performing necessary compliance maintenance associated with Jobs #909843, #148828, #148835, #909850, and #43687 on its 2025 Planned Outage and Maintenance Summary. The maintenance outages will impact the availability of primary-firm transportation services moving north to south through Compressor Station 155. The current schedule is April 29, 2025 through July 1, 2025.  During this period of planned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving north to south through the location listed below may not be available.

Operating Conditions resulting from this work will also require Transco to manage primary-firm transportation services moving north to south through the TSB location listed below. The total quantity available will be contingent on system conditions during the maintenance period and is anticipated to be initially limited to the quantities indicated below. Transactions moving south to north through this location will not be impacted.

The receipt-based Throughput Section Boundary (TSB) at MAINLINE MP 1326 will be used to manage capacity availability including any required changes to the expected total quantities available during this planned work indicated below. An updated Market and Production Area constraint notice will include the location and the available quantity of primary-firm transportation services during the indicated periods. 

TSB Name - Location

Location ID

Flow Direction

MAINLINE MP 1326 TSB

 9012983

North to South

 

 

 Estimated Outage

Design Capacity (Mdt/d)

Total Primary-Firm Quantity Available (Mdt/d)

% Cuts (Primary) – Potential Shipper Impact (Based on Historical Utilization)*

April 29 – May 15

2,460

2,460

N/A

May 16 – May 26

2,460

2,100

0-10%

May 27 – June 3

2,460

2,460

N/A

June 4 – July 1

2,460

2,100

0-10%

 

 *% Cuts (Primary) is an estimate of the impact to shippers based on historical utilization and anticipated volumes during the time of constraint. These amounts are subject to change based on actual nominated volumes and changes in the amount of available capacity.

If you have any questions, please contact your Transportation Services Representative.

TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC
Critical: Y
Notice Eff Date: 04/08/2025
Notice Eff Time: 09:51:37 CDT
Notice End Date:
Notice End Time:
Notice ID: 15551159
Notice Stat Desc: Initiate
Notice Type Desc: Maint
Post Date: 04/08/2025
Post Time: 09:51:37 CDT
Prior Notice: 0
Reqrd Rsp Desc: Immediate response required of an operational nature may be required of impacted shippers
Rsp Date:
Rsp Time:
TSP: 007933021
TSP Name: TRANSCONTINENTAL GAS PIPE LINE COMPANY, LLC

Notice Text:

Subject: Station 155 Planned Outage and Maintenance Summary

Transco will be performing necessary compliance maintenance associated with Jobs #909843, #148828, #148835, #909850, and #43687 on its 2025 Planned Outage and Maintenance Summary. The maintenance outages will impact the availability of primary-firm transportation services moving north to south through Compressor Station 155. The current schedule is April 29, 2025 through July 1, 2025.  During this period of planned maintenance, non-secondary reverse path (NSRP), secondary FT, and interruptible (IT) transactions moving north to south through the location listed below may not be available.

Operating Conditions resulting from this work will also require Transco to manage primary-firm transportation services moving north to south through the TSB location listed below. The total quantity available will be contingent on system conditions during the maintenance period and is anticipated to be initially limited to the quantities indicated below. Transactions moving south to north through this location will not be impacted.

The receipt-based Throughput Section Boundary (TSB) at MAINLINE MP 1326 will be used to manage capacity availability including any required changes to the expected total quantities available during this planned work indicated below. An updated Market and Production Area constraint notice will include the location and the available quantity of primary-firm transportation services during the indicated periods. 

TSB Name - Location

Location ID

Flow Direction

MAINLINE MP 1326 TSB

 9012983

North to South

 

 

 Estimated Outage

Design Capacity (Mdt/d)

Total Primary-Firm Quantity Available (Mdt/d)

% Cuts (Primary) – Potential Shipper Impact (Based on Historical Utilization)*

April 29 – May 15

2,460

2,460

N/A

May 16 – May 26

2,460

2,100

0-10%

May 27 – June 3

2,460

2,460

N/A

June 4 – July 1

2,460

2,100

0-10%

 

 *% Cuts (Primary) is an estimate of the impact to shippers based on historical utilization and anticipated volumes during the time of constraint. These amounts are subject to change based on actual nominated volumes and changes in the amount of available capacity.

If you have any questions, please contact your Transportation Services Representative.