Columbia Gas Transmission Notice 25916630
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
|
TSP Name
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
25916630
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
10/24/24
10/24/24
11/24/24
2:45:43 PM
12:00:00 AM
12:00:00 AM
Subject: Construction and Maintenance Schedule Posting
Author: Dillon Schoolcraft
Notice Text
As a courtesy, Columbia Gas Transmission, LLC (TCO) hereby notifies customers the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website has been updated. TCO reminds customers to please check the Maintenance Schedule on a regular basis. The current schedule has been updated to reflect maintenance activity on the following: * Revised end date – BM39 Pipe Replacement – September 19, 2024-November 8, 2024 (Previously scheduled to end on October 25, 2024)* Line 1804 pigging – December 3-6, 2024
Additionally, the following file(s) can be located on Informational Postings under Construction and Maintenance
TCO Construction and Maintenance Schedule 10-24-2024.pdf
Columbia Gas Transmission, LLC
TSP
054748041
Date
Time
Notice ID
25916630
Notice Type Description: Maintenance
Notice Stat Desc: Initiate
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No Response Required
Post
Notice Effective
Notice End
Response
10/24/24
10/24/24
11/24/24
2:45:43 PM
12:00:00 AM
12:00:00 AM
Subject: Construction and Maintenance Schedule Posting
Author: Dillon Schoolcraft
Notice Text
As a courtesy, Columbia Gas Transmission, LLC (TCO) hereby notifies customers the Construction and Maintenance Schedule posted under "Construction and Maintenance" on the Informational Postings website has been updated. TCO reminds customers to please check the Maintenance Schedule on a regular basis. The current schedule has been updated to reflect maintenance activity on the following: * Revised end date – BM39 Pipe Replacement – September 19, 2024-November 8, 2024 (Previously scheduled to end on October 25, 2024)* Line 1804 pigging – December 3-6, 2024
Additionally, the following file(s) can be located on Informational Postings under Construction and Maintenance
TCO Construction and Maintenance Schedule 10-24-2024.pdf