TSP: 117613169

TSP Name: Double E

Posting Date/Time: 06/02/2022 09:29:32

Notice Identifier: DOWNSTREAM MAINTENANCE GCX

Notice Stat Desc: Initiate

Notice Type Desc: Maintenance

Notice Category: Critical

Subject: Gulf Coast Express - Liner Repair at Devils River Compressor Station

Notice Eff Date/Time: 06/02/2022 00:00:00

Notice End Date/Time: 06/22/2022 00:00:00

Critical Desc: Yes

Notice Scope: TSP SPECIFIC

Reqrd Rsp Desc: No

Response Date/Time:

Prior Notice Identifier:

Notice Text:
Gulf Coast Express Pipeline LLC (GCX) will be performing repairs at Devils River Compressor Station, and the total capacity on GCX will be reduced to 1,850,000 MMBtu. The reduction will begin Tuesday, June 14, 2022 and GCX is expected to be back to full capacity on Tuesday, June 21, 2022.

Double E shippers who are planning on taking gas to that deliver point this month should contact their GCX account representatives for information regarding their prorated FIRM MDQ.

GCX will post updates if there are any changes to this schedule. Should you have any additional questions concerning this notice, check the Informational Postings on the Kinder Morgan DART website, or contact your commercial rep.





TSP: 117613169

TSP Name: Double E

Posting Date/Time: 06/02/2022 09:29:32

Notice Identifier: DOWNSTREAM MAINTENANCE GCX

Notice Stat Desc: Initiate

Notice Type Desc: Maintenance

Notice Category: Critical

Subject: Gulf Coast Express - Liner Repair at Devils River Compressor Station

Notice Eff Date/Time: 06/02/2022 00:00:00

Notice End Date/Time: 06/22/2022 00:00:00

Critical Desc: Yes

Notice Scope: TSP SPECIFIC

Reqrd Rsp Desc: No

Response Date/Time:

Prior Notice Identifier:

Notice Text:
Gulf Coast Express Pipeline LLC (GCX) will be performing repairs at Devils River Compressor Station, and the total capacity on GCX will be reduced to 1,850,000 MMBtu. The reduction will begin Tuesday, June 14, 2022 and GCX is expected to be back to full capacity on Tuesday, June 21, 2022.

Double E shippers who are planning on taking gas to that deliver point this month should contact their GCX account representatives for information regarding their prorated FIRM MDQ.

GCX will post updates if there are any changes to this schedule. Should you have any additional questions concerning this notice, check the Informational Postings on the Kinder Morgan DART website, or contact your commercial rep.