ame / TSP: EASTERN GAS TRANSMISSION AND STORAGE INC (116025180)
C
ritical: Y
P
osting Date/Time: 01/02/2025 08:28 AM
N
otice Stat Desc: Initiate
N
otice Eff Date/Time: 01/04/2025 09:00 AM
N
otice ID: 1004013
P
rior Notice:
R
eqrd Rsp Desc: No response required
R
esponse Date/Time:
N
otice Type Desc: OFO
S
ubject: OFO ADVISORY Northern FTNN Hourly
N
otice Text:
E
ective with the
start of Gas Day Saturday, January 4, 2025, and continuing until further notice, the following Advisory
shall be in effect on the EGTS system:
B
asis for Advisory:
D
ue to a significant drop in forecasted temperatures along with anticipated system utilization and operating conditions,
EGTS
has determined that hourly quantities delivered to Customers at the Delivery Point(s) listed below may be in excess of
the quantities that EGTS can deliver without jeopardizing its ability to provide firm transportation services to other
C
ustomers.
C
ustomer Action Required:
E
ach affected Customer will take whatever action it may deem appropriate, including notification of IT shippers at affected
D
elivery Point(s). Pursuant to Section 9.5.A of Rate Schedule FTNN in EGTS’ FERC Gas Tariff, EGTS hereby provides four (4)
hours advance notice that it may issue an OFO that will require Customers to limit delivery fluctuations to the areas within
one (1) hour. At that time, Customers in the locations listed below must reduce deliveries from EGTS at specified Delivery
P
oint(s) to the levels as stated in Section 9.5D of Rate Schedule FTNN Tariff Record 20.2 of EGTS’ FERC Gas Tariff. Customers
that do not have specified MDDO(s) at affected Delivery Point(s) will also be required to reduce their delivery from EGTS to
their MDTQ levels as stated in Section 9.5.A of Rate Schedule FTNN in EGTS’ FERC Gas Tariff.
A
reas Affected:
S
ystems in the Northern portion of the EGTS operating area. More specifically, the following locations are impacted by this
OFO
A
dvisory:
L
ocation Name
L
ocation
C
orning Natural Gas
21000
N
ew York State Electric & Gas
20700
A
rlington Storage (Seneca)
20720
R
ochester Gas and Electric
20600
A
llegany Generation
23632
N
iagara Mohawk
20500
and 20550
F
illmore Gas
23600
N
ational Fuel Gas Distribution
20900
S
teuben Storage
90005
Page 2
L
ocation Name
L
ocation
A
lliance/Lower Leroy
30005
W
oodhull
23700
I
ndeck Silver Springs
30001
T
ioga UGI Storage
90002
T
ioga R-Gate
90008
C
ornell
30170
P
lease continue to monitor these postings for further updates. If you have any questions, please contact your Customer
T
ransportation Representative or Interstate Marketing Manager.
Critical: Y
Posting Date/Time: 01/02/2025 08:28 AM
Notice Stat Desc: Initiate
Notice Eff Date/Time: 01/04/2025 09:00 AM
Notice ID: 1004013
Prior Notice:
Reqrd Rsp Desc: No response required
Response Date/Time:
Notice Type Desc: OFO
Subject: OFO ADVISORY Northern FTNN Hourly
Notice Text:
Effective with the start of Gas Day Saturday, January 4, 2025, and continuing until further notice, the following Advisory
shall be in effect on the EGTS system:
Basis for Advisory:
Due to a significant drop in forecasted temperatures along with anticipated system utilization and operating conditions,
EGTS has determined that hourly quantities delivered to Customers at the Delivery Point(s) listed below may be in excess of
the quantities that EGTS can deliver without jeopardizing its ability to provide firm transportation services to other
Customers.
Customer Action Required:
Each affected Customer will take whatever action it may deem appropriate, including notification of IT shippers at affected
Delivery Point(s). Pursuant to Section 9.5.A of Rate Schedule FTNN in EGTS’ FERC Gas Tariff, EGTS hereby provides four (4)
hours advance notice that it may issue an OFO that will require Customers to limit delivery fluctuations to the areas within
one (1) hour. At that time, Customers in the locations listed below must reduce deliveries from EGTS at specified Delivery
Point(s) to the levels as stated in Section 9.5D of Rate Schedule FTNN Tariff Record 20.2 of EGTS’ FERC Gas Tariff. Customers
that do not have specified MDDO(s) at affected Delivery Point(s) will also be required to reduce their delivery from EGTS to
their MDTQ levels as stated in Section 9.5.A of Rate Schedule FTNN in EGTS’ FERC Gas Tariff.
Areas Affected:
Systems in the Northern portion of the EGTS operating area. More specifically, the following locations are impacted by this
OFO Advisory:
Location Name
Location
Corning Natural Gas
21000
New York State Electric & Gas
20700
Arlington Storage (Seneca)
20720
Rochester Gas and Electric
20600
Allegany Generation
23632
Niagara Mohawk
20500 and 20550
Fillmore Gas
23600
National Fuel Gas Distribution
20900
Steuben Storage
90005
Page 1
Location Name
Location
Alliance/Lower Leroy
30005
Woodhull
23700
Indeck Silver Springs
30001
Tioga UGI Storage
90002
Tioga R-Gate
90008
Cornell
30170
Please continue to monitor these postings for further updates. If you have any questions, please contact your Customer
Transportation Representative or Interstate Marketing Manager.
Page 2