Equitrans Notice 111154
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
System Wide Notice Detail
TSP Name: EQUITRANS (TSP: 189569585)
12/21/2024 8:16 PM
Page 1 of 2
TSP Name / TSP:
EQUITRANS (189569585)
Post Date/Time:
04-18-2024 01:30:00 PM
Subject:
H-117 Pipeline Smart Pig Run 04-25-24 Update 2
Notice Type:
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE
Notice ID:
111154
Prior Notice ID:
111135
Notice Status Description:
Supersede
Critical Notice Description:
Critical Notice
Notice Effective Date:
04-18-2024
Notice Effective Time:
01:30:00 PM
Notice End Date:
07-31-2024
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
NO RESPONSE REQUIRED
System Wide Notice Detail
TSP Name: EQUITRANS (TSP: 189569585)
12/21/2024 8:16 PM
Page 2 of 2
Notice Text:
Equitrans L.P is providing notice that the H-117 Pipeline smart pig run that was postponed until further notice has been rescheduled for
Thursday April 25, 2024.
Equitrans L.P. will be conducting a pipeline smart pig run on its H-117 Pipeline in Mainline Operational Area 2 from Pratt MR to Goodwin Gates
beginning at 10:00 AM ET on April 25, 2024, and is issuing an OFO in accordance with Section 6.11 of the General Terms and Conditions of its
FERC Gas Tariff.
Equitrans L.P is hereby providing notice that due to the high possibility of fluids during the pig run the following?all People’s Natural Gas
Delivery/Receipt Meters between Pratt MR Coordinates (39.912559 / -80.128427) and the Goodwin Gates Coordinates (39.822237 / -
80.213766) on the H-117 Pipeline must be shut in by 10:00 AM ET on April 25, 2024, and remain shut in for the duration of the pigging, which is
estimated to last 5 hours.
Additionally, in conjunction with this pigging, Operational Capacity at the TCO Interconnects (PickenPaw Meter # 24438 and Rhinehart Meter #
11169) will be reduced to 100,000 Dths for April 25, 2024, Gas Day. The Operationally Available Capacity is posted by meter; however,
nominations will be scheduled to not exceed 100,000 DTHs in total TCO deliveries regardless of the actual meter split.
Next, in conjunction with this pigging, the following Customer Receipt Meters: #M5424301 and #5424306 (Whites Ridge), must be shut in by
10:00 AM ET on April 25, 2024, and remain shut in for the during of the pigging, which has an estimated duration of 5 hours. Nominations should
be adjusted accordingly.
Lastly, in conjunction with this pigging, fluctuations in pipeline pressures on the H-117, D-497, and H-322 pipeline are to be expected. Lower
pipelines pressures could impact deliverability to meter, M5354179 (HTEC IC).
If Customer and/or Customer’s operator fails to comply with the terms of this OFO, such Customer shall be subject to (1) liability for any
damages including, but not limited to, direct, consequential, exemplary, or punitive damages incurred by Equitrans or any other party as a result
of such failure, (2) a penalty of $25 per Dth times the quantity of gas by which the Customer deviated from the requirements of this OFO, (3) flow
control, and/or (4) a reduction in scheduled quantities to match flowing gas. In addition, Equitrans will not permit post-cycle adjustments to avoid
an OFO penalty.
Customers should monitor Equitrans’ Informational Postings website for updates to this notice.
The estimated duration of the pigging is 5 hours. Upon completion of the maintenance the OFO will expire and Equitrans L.P. will notify impacted
parties when they can turn back in-line.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
TSP Name: EQUITRANS (TSP: 189569585)
TSP Name / TSP:
EQUITRANS (189569585)
Post Date/Time:
04-18-2024 01:30:00 PM
Subject:
H-117 Pipeline Smart Pig Run 04-25-24 Update 2
Notice Type:
OPERATIONAL FLOW ORDER/PLANNED SERVICE OUTAGE
Notice ID:
111154
Prior Notice ID:
111135
Notice Status Description:
Supersede
Critical Notice Description:
Critical Notice
Notice Effective Date:
04-18-2024
Notice Effective Time:
01:30:00 PM
Notice End Date:
07-31-2024
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
NO RESPONSE REQUIRED
12/21/2024 8:16 PM
Page 1 of 2
System Wide Notice Detail
TSP Name: EQUITRANS (TSP: 189569585)
Notice Text:
Equitrans L.P is providing notice that the H-117 Pipeline smart pig run that was postponed until further notice has been rescheduled for
Thursday April 25, 2024.
Equitrans L.P. will be conducting a pipeline smart pig run on its H-117 Pipeline in Mainline Operational Area 2 from Pratt MR to Goodwin Gates
beginning at 10:00 AM ET on April 25, 2024, and is issuing an OFO in accordance with Section 6.11 of the General Terms and Conditions of its
FERC Gas Tariff.
Equitrans L.P is hereby providing notice that due to the high possibility of fluids during the pig run the following?all People’s Natural Gas
Delivery/Receipt Meters between Pratt MR Coordinates (39.912559 / -80.128427) and the Goodwin Gates Coordinates (39.822237 / -
80.213766) on the H-117 Pipeline must be shut in by 10:00 AM ET on April 25, 2024, and remain shut in for the duration of the pigging, which is
estimated to last 5 hours.
Additionally, in conjunction with this pigging, Operational Capacity at the TCO Interconnects (PickenPaw Meter # 24438 and Rhinehart Meter #
11169) will be reduced to 100,000 Dths for April 25, 2024, Gas Day. The Operationally Available Capacity is posted by meter; however,
nominations will be scheduled to not exceed 100,000 DTHs in total TCO deliveries regardless of the actual meter split.
Next, in conjunction with this pigging, the following Customer Receipt Meters: #M5424301 and #5424306 (Whites Ridge), must be shut in by
10:00 AM ET on April 25, 2024, and remain shut in for the during of the pigging, which has an estimated duration of 5 hours. Nominations should
be adjusted accordingly.
Lastly, in conjunction with this pigging, fluctuations in pipeline pressures on the H-117, D-497, and H-322 pipeline are to be expected. Lower
pipelines pressures could impact deliverability to meter, M5354179 (HTEC IC).
If Customer and/or Customer’s operator fails to comply with the terms of this OFO, such Customer shall be subject to (1) liability for any
damages including, but not limited to, direct, consequential, exemplary, or punitive damages incurred by Equitrans or any other party as a result
of such failure, (2) a penalty of $25 per Dth times the quantity of gas by which the Customer deviated from the requirements of this OFO, (3) flow
control, and/or (4) a reduction in scheduled quantities to match flowing gas. In addition, Equitrans will not permit post-cycle adjustments to avoid
an OFO penalty.
Customers should monitor Equitrans’ Informational Postings website for updates to this notice.
The estimated duration of the pigging is 5 hours. Upon completion of the maintenance the OFO will expire and Equitrans L.P. will notify impacted
parties when they can turn back in-line.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.
12/21/2024 8:16 PM
Page 2 of 2