TSP Name: EQUITRANS (TSP: 189569585)

2/22/2025 12:58 PM

Page 1 of 1

TSP Name / TSP:

EQUITRANS (189569585)

Post Date/Time:

12-05-2024 09:50:00 AM

Subject:

Plasma Compressor Station Unplanned Maintenance 12-05-24

Notice Type:

CURTAILMENT

Notice ID:

117899

Notice Status Description:

Initiate

Critical Notice Description:

Critical Notice

Notice Effective Date:

12-05-2024

Notice Effective Time:

09:50:00 AM

Notice End Date:

03-31-2025

Notice End Time:

12:00:00 AM

Required Response Indicator Description:

NO RESPONSE REQUIRED

Notice Text:

Equitrans L.P. is providing notice of unplanned maintenance at its Plasma Compressor Station in its Mainline Operational Area 3 starting
December 05, 2024, Gas Day, and until further notice. EQT Midstream personnel are onsite working to resolve this issue and do not yet have a
return to service timeline; however, updates will be posted as additional information becomes available.

In conjunction with this maintenance, Operationally Available Capacity through the Plasma_OVC Meter is being reduced to Net Delivered
Operational Capacities of 935,000 Dths starting with Intraday 1 cycle of December 05, 2024, Gas Day, and until further notice.

Scheduled Quantities will be adjusted to not exceed this amount. This amount is based on projected operating conditions and is subject to
change.

Net Delivered Dths are calculated by netting Receipt and Delivery Scheduled Quantities at the Plasma _OVC Meter listed above.

Nominations will be scheduled in accordance with Section 6.8 of the General Terms and Conditions of Equitrans’ FERC Gas Tariff. Intraday
nomination changes may be permitted should the actual outage timeframe or level of impact differ from the estimates stated in this notification.

In addition, Customers may experience higher than normal pressures on the following pipelines in Mainline Operational Area 3 and Mainline
Operational Area 4: H-302, H-306, H-310, GSF-912, GSF-993, H-557, GSF-604, H-527, H-515, H-518, H-511, H-509, and H-508.

Customers should monitor Equitrans’ Informational Postings Website for updates to this notice and applicable posted Operationally Available
Capacity.

*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.

System Wide Notice Detail
TSP Name: EQUITRANS (TSP: 189569585)
TSP Name / TSP:
EQUITRANS (189569585)
Post Date/Time:
12-05-2024 09:50:00 AM
Subject:
Plasma Compressor Station Unplanned Maintenance 12-05-24
Notice Type:
CURTAILMENT
Notice ID:
117899
Notice Status Description:
Initiate
Critical Notice Description:
Critical Notice
Notice Effective Date:
12-05-2024
Notice Effective Time:
09:50:00 AM
Notice End Date:
03-31-2025
Notice End Time:
12:00:00 AM
Required Response Indicator Description:
NO RESPONSE REQUIRED
Notice Text:
Equitrans L.P. is providing notice of unplanned maintenance at its Plasma Compressor Station in its Mainline Operational Area 3 starting
December 05, 2024, Gas Day, and until further notice. EQT Midstream personnel are onsite working to resolve this issue and do not yet have a
return to service timeline; however, updates will be posted as additional information becomes available.
In conjunction with this maintenance, Operationally Available Capacity through the Plasma_OVC Meter is being reduced to Net Delivered
Operational Capacities of 935,000 Dths starting with Intraday 1 cycle of December 05, 2024, Gas Day, and until further notice.
Scheduled Quantities will be adjusted to not exceed this amount. This amount is based on projected operating conditions and is subject to
change.
Net Delivered Dths are calculated by netting Receipt and Delivery Scheduled Quantities at the Plasma _OVC Meter listed above.
Nominations will be scheduled in accordance with Section 6.8 of the General Terms and Conditions of Equitrans’ FERC Gas Tariff. Intraday
nomination changes may be permitted should the actual outage timeframe or level of impact differ from the estimates stated in this notification.
In addition, Customers may experience higher than normal pressures on the following pipelines in Mainline Operational Area 3 and Mainline
Operational Area 4: H-302, H-306, H-310, GSF-912, GSF-993, H-557, GSF-604, H-527, H-515, H-518, H-511, H-509, and H-508.
Customers should monitor Equitrans’ Informational Postings Website for updates to this notice and applicable posted Operationally Available
Capacity.
*This data represents data available within the last 3 months. For prior data to this time period, please contact your customer service representative.