Gulf Coast Express Pipeline Notice 203698

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  81252229-GULF COAST EXPRESS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  10/21/2024 2:19:00PM Notice End Date/Time:  10/22/2024 9:00:00am
Post Date/Time:  10/21/2024 2:19:00 PM Notice ID: 203698
Reqrd Rsp:  5 Rsp Date: 
Notice Stat Desc:  SUPERSEDE Prior Notice:  203693
Subject:  Reminder: GCX Inspections & ESD Testing
Notice Text:

Reminder: GCX Inspections & ESD Testing

As a reminder, beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.

 

 

Previously Posted on 9/23/24

Beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.

TSP/TSP Name:  81252229-GULF COAST EXPRESS PIPELINE Critical: Y
Notice Type Desc (1):  MAINTENANCE Notice Type Desc (2):  MAINTENANCE
Notice Eff Date/Time:  10/21/2024 2:19:00PM Notice End Date/Time:  10/22/2024 9:00:00am
Post Date/Time:  10/21/2024 2:19:00 PM Notice ID: 203698
Reqrd Rsp:  5 Rsp Date: 
Notice Stat Desc:  SUPERSEDE Prior Notice:  203693
Subject:  Reminder: GCX Inspections & ESD Testing
Notice Text:

Reminder: GCX Inspections & ESD Testing

As a reminder, beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.

 

 

Previously Posted on 9/23/24

Beginning the Gas Day of Tuesday, October 29, 2024, through and including the Gas Day of Saturday, November 2, 2024, GCX operations will be performing ESD tests at Waha C/S as well as warranty inspections and ESD testing at Devils River C/S, Rankin C/S, and Big Wells C/S.  During these maintenances, the total Mainline capacity on GCX will be as follows:

 

Tuesday, October 29th

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,200,000 MMBtu

-          All Waha location deliveries will be limited to displacement only

Wednesday, October 30th – Saturday, November 2nd

-          Total Mainline capacity on GCX reduced from 2,020,000 MMBtu to 1,630,000 MMBtu

 

Should you have any questions, please contact your GCX Account Representative.