Gulf South Pipeline Notice 5035313
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Notice
Critical / Planned Service Outage
TSP:
Post Date/Time:
78444247
08/08/2024 12:58:35PM
Category:
TSP Name: Gulf South Pipeline Company, LLC
Notice Effective Date/Time: 10/15/2024 09:00:00AM
Notice Type Desc: Maintenance
UPDATE: Brazos Compressor Station Maintenance
Subject:
Supersede
5035313
Notice Stat Desc:
Prior Notice:
Notice ID:
Response Date/Time:
Reqrd Rsp Desc:
Notice End Date/Time: 10/19/2024 09:00:00 AM
Critical: Y
5035197
No response required
UPDATE: Demand charge credit update
--------------------------------------------------------------------------------
Gulf South will be performing maintenance at the Brazos Compressor Station.
The following scheduling group is subject to impact:
West 30 From Magasco to South Texas (Del)
Capacity could be impacted by as much as 200,000 dth/d for the duration of the maintenance. Anticipated
impact to all services including Primary Firm.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South's NGA Gas Tariff.
Please contact your customer service representative with any questions.
Notice Text:
08/08/2024 12:59:44PM
Page 1 of 1
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical / Planned Service Outage
Post Date/Time: 08/08/2024 12:58:35PM
Notice Type Desc: Maintenance
Notice Effective Date/Time: 10/15/2024 09:00:00AM
Notice Stat Desc: Supersede
Notice End Date/Time: 10/19/2024 09:00:00 AM
Notice ID: 5035313
Response Date/Time:
Prior Notice: 5035197
Critical: Y
Reqrd Rsp Desc: No response required
Subject: UPDATE: Brazos Compressor Station Maintenance
Notice Text:
UPDATE: Demand charge credit update
--------------------------------------------------------------------------------
Gulf South will be performing maintenance at the Brazos Compressor Station.
The following scheduling group is subject to impact:
West 30 From Magasco to South Texas (Del)
Capacity could be impacted by as much as 200,000 dth/d for the duration of the maintenance. Anticipated
impact to all services including Primary Firm.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South's NGA Gas Tariff.
Please contact your customer service representative with any questions.