Gulf South Pipeline Notice 5035469

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice

Critical / Planned Service Outage

TSP:

Post Date/Time:

78444247

10/04/2024 01:15:04PM

Category:

TSP Name: Gulf South Pipeline Company, LLC

Notice Effective Date/Time: 10/20/2024 09:00:00AM

Notice Type Desc: Maintenance

UPDATE: Harrisville Compressor Station Maintenance

Subject:

Supersede

5035469

Notice Stat Desc:

Prior Notice:

Notice ID:

Response Date/Time:

Reqrd Rsp Desc:

Notice End Date/Time: 10/28/2024 09:00:00 AM

Critical: Y

5035420

No response required

UPDATE: Revised dates.
-----------------------------------------------------------------------------------
UPDATE: Revised End Date in description
-----------------------------------------------------------------------------------
UPDATE: Revised Dates
-----------------------------------------------------------------------------------
UPDATE: Demand charge credit update
-----------------------------------------------------------------------------------
UPDATE: Revised End Date

Gulf South will be performing maintenance at the Harrisville Compressor Station.

The following scheduling group is subject to impact:

Expansion Area 19 Deliveries

10/20:

Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.

10/21 - 10/27:

Capacity could be impacted by as much as 250,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Service.

Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.

Notice Text:

10/04/2024 1:16:29PM

Page 1 of 2

Please contact your customer service representative with any questions.

10/04/2024 1:16:29PM

Page 2 of 2

Notice
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical / Planned Service Outage
Post Date/Time: 10/04/2024 01:15:04PM
Notice Type Desc: Maintenance
Notice Effective Date/Time: 10/20/2024 09:00:00AM
Notice Stat Desc: Supersede
Notice End Date/Time: 10/28/2024 09:00:00 AM
Notice ID: 5035469
Response Date/Time:
Prior Notice: 5035420
Critical: Y
Reqrd Rsp Desc: No response required
Subject: UPDATE: Harrisville Compressor Station Maintenance
Notice Text:
UPDATE: Revised dates.
-----------------------------------------------------------------------------------
UPDATE: Revised End Date in description
-----------------------------------------------------------------------------------
UPDATE: Revised Dates
-----------------------------------------------------------------------------------
UPDATE: Demand charge credit update
-----------------------------------------------------------------------------------
UPDATE: Revised End Date
Gulf South will be performing maintenance at the Harrisville Compressor Station.
The following scheduling group is subject to impact:
Expansion Area 19 Deliveries
10/20:
Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.
10/21 - 10/27:
Capacity could be impacted by as much as 250,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Service.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.
10/04/2024 1:16:29PM
Page 1 of 2

Please contact your customer service representative with any questions.
10/04/2024 1:16:29PM
Page 2 of 2