Gulf South Pipeline Notice 5035773

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice

Critical

TSP:

Post Date/Time:

78444247

12/16/2024 03:43:42PM

Category:

TSP Name: Gulf South Pipeline Company, LLC

Notice Effective Date/Time: 04/07/2025 09:00:00AM

Notice Type Desc: Maintenance

Harrisville Compressor Station Maintenance

Subject:

Initiate

5035773

Notice Stat Desc:

Prior Notice:

Notice ID:

Response Date/Time:

Reqrd Rsp Desc:

Notice End Date/Time: 04/10/2025 09:00:00 AM

Critical: Y

No response required

Gulf South will be performing maintenance at the Harrisville Compressor Station

Following scheduling group is subject to impact:

Expansion Area 19 Delivery Scheduling Group

Gas Day 4/7:

Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.

Gas Day 4/8 - 4/9:

Capacity could be impacted by as much as 250,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Serivce.

Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.
"

Notice Text:

12/16/2024 3:46:24PM

Page 1 of 1

Notice
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical
Post Date/Time: 12/16/2024 03:43:42PM
Notice Type Desc: Maintenance
Notice Effective Date/Time: 04/07/2025 09:00:00AM
Notice Stat Desc: Initiate
Notice End Date/Time: 04/10/2025 09:00:00 AM
Notice ID: 5035773
Response Date/Time:
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No response required
Subject: Harrisville Compressor Station Maintenance
Notice Text:
Gulf South will be performing maintenance at the Harrisville Compressor Station
Following scheduling group is subject to impact:
Expansion Area 19 Delivery Scheduling Group
Gas Day 4/7:
Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.
Gas Day 4/8 - 4/9:
Capacity could be impacted by as much as 250,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Serivce.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.
"
12/16/2024 3:46:24PM
Page 1 of 1