Gulf South Pipeline Notice 5036021
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Notice
Critical / Planned Service Outage
TSP:
Post Date/Time:
78444247
02/11/2025 10:45:33AM
Category:
TSP Name: Gulf South Pipeline Company, LLC
Notice Effective Date/Time: 03/24/2025 09:00:00AM
Notice Type Desc: Maintenance
Wilson Compressor Station Maintenance
Subject:
Initiate
5036021
Notice Stat Desc:
Prior Notice:
Notice ID:
Response Date/Time:
Reqrd Rsp Desc:
Notice End Date/Time: 03/27/2025 09:00:00 AM
Critical: Y
No response required
Wilson Compressor South Scheduling Group:
-------------------------------------------------------------------------
Gas Day 3/24:
Capacity could be impacted by as much as 150,000 dth/d for the duration of the maintenance. Primary Firm
will be impacted.
Gas Day 3/25:
Due to required compliance testing at Wilson Compressor Station, capacity could be impacted by as much as
1,270,000 dth/d until ID2 before dropping to a 150,000 dth/d impact for the remainder of the gas day.
Capacity will be impacted by as much as 570,000 dth/d for the gas day. Primary Firm will be impacted.
"Due to required compliance testing at Wilson Compressor Station, the following meter will need to be
shut-in during the duration of the 9-hr maintenance on Gas Day 3/25:
- Loc 23376 (Coastal Bend (Enterprise))
Gas Day 3/26:
Capacity could be impacted by as much as 150,000 dth/d for the duration of the maintenance. Primary Firm
will be impacted.
Notice Text:
02/11/2025 10:46:26AM
Page 1 of 1
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical / Planned Service Outage
Post Date/Time: 02/11/2025 10:45:33AM
Notice Type Desc: Maintenance
Notice Effective Date/Time: 03/24/2025 09:00:00AM
Notice Stat Desc: Initiate
Notice End Date/Time: 03/27/2025 09:00:00 AM
Notice ID: 5036021
Response Date/Time:
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No response required
Subject: Wilson Compressor Station Maintenance
Notice Text:
Wilson Compressor South Scheduling Group:
-------------------------------------------------------------------------
Gas Day 3/24:
Capacity could be impacted by as much as 150,000 dth/d for the duration of the maintenance. Primary Firm
will be impacted.
Gas Day 3/25:
Due to required compliance testing at Wilson Compressor Station, capacity could be impacted by as much as
1,270,000 dth/d until ID2 before dropping to a 150,000 dth/d impact for the remainder of the gas day.
Capacity will be impacted by as much as 570,000 dth/d for the gas day. Primary Firm will be impacted.
"Due to required compliance testing at Wilson Compressor Station, the following meter will need to be
shut-in during the duration of the 9-hr maintenance on Gas Day 3/25:
- Loc 23376 (Coastal Bend (Enterprise))
Gas Day 3/26:
Capacity could be impacted by as much as 150,000 dth/d for the duration of the maintenance. Primary Firm
will be impacted.
02/11/2025 10:46:26AM
Page 1 of 1