Gulf South Pipeline Notice 5036290

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice

Critical

TSP:

Post Date/Time:

78444247

03/28/2025 02:26:26PM

Category:

TSP Name: Gulf South Pipeline Company, LLC

Notice Effective Date/Time: 04/28/2025 09:00:00AM

Notice Type Desc: Maintenance

Index 363 Pipeline Maintenance

Subject:

Initiate

5036290

Notice Stat Desc:

Prior Notice:

Notice ID:

Response Date/Time:

Reqrd Rsp Desc:

Notice End Date/Time: 05/04/2025 09:00:00 AM

Critical: Y

No response required

Gulf South is performing work on Index 363.

Gulf South will work with the following point operators to mitigate impact:

- Loc 8563 (Avery Island Farm Gate #1)
- 4 Centerpoint Rural Taps
- 17 Centerpoint Farm Taps

The following scheduling group is subject to impact:

Bayou Sale to Napoleonville Scheduling Group

Capacity could be impacted by as much as 200,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Serivce.

Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.

If you have any questions, please contact your customer service representative.

Notice Text:

03/28/2025 2:30:34PM

Page 1 of 1

Notice
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical
Post Date/Time: 03/28/2025 02:26:26PM
Notice Type Desc: Maintenance
Notice Effective Date/Time: 04/28/2025 09:00:00AM
Notice Stat Desc: Initiate
Notice End Date/Time: 05/04/2025 09:00:00 AM
Notice ID: 5036290
Response Date/Time:
Prior Notice:
Critical: Y
Reqrd Rsp Desc: No response required
Subject: Index 363 Pipeline Maintenance
Notice Text:
Gulf South is performing work on Index 363.
Gulf South will work with the following point operators to mitigate impact:
- Loc 8563 (Avery Island Farm Gate #1)
- 4 Centerpoint Rural Taps
- 17 Centerpoint Farm Taps
The following scheduling group is subject to impact:
Bayou Sale to Napoleonville Scheduling Group
Capacity could be impacted by as much as 200,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Serivce.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.
If you have any questions, please contact your customer service representative.
03/28/2025 2:30:34PM