Gulf South Pipeline Notice 5036323

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice

Critical / Planned Service Outage

TSP:

Post Date/Time:

78444247

04/02/2025 12:22:36PM

Category:

TSP Name: Gulf South Pipeline Company, LLC

Notice Effective Date/Time: 05/11/2025 09:00:00AM

Notice Type Desc: Maintenance / Planned Service Outage

Marksville Compressor Station Maintenance

Subject:

Terminate

5036323

Notice Stat Desc:

Prior Notice:

Notice ID:

Response Date/Time:

Reqrd Rsp Desc:

Notice End Date/Time: 05/17/2025 09:00:00 AM

Critical: Y

5036118

No response required

Marksville Deliveries Scheduling Group

Gas Day 5/11:

Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.

Gas Day 5/12 - 5/16:

Capacity could be impacted by as much as 250,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Serivce.

Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.

If you have any questions, please contact your customer service representative.

Notice Text:

04/02/2025 12:26:57PM

Page 1 of 1

Notice
TSP Name: Gulf South Pipeline Company, LLC
TSP: 78444247
Category: Critical / Planned Service Outage
Post Date/Time: 04/02/2025 12:22:36PM
Notice Type Desc: Maintenance / Planned Service Outage
Notice Effective Date/Time: 05/11/2025 09:00:00AM
Notice Stat Desc: Terminate
Notice End Date/Time: 05/17/2025 09:00:00 AM
Notice ID: 5036323
Response Date/Time:
Prior Notice: 5036118
Critical: Y
Reqrd Rsp Desc: No response required
Subject: Marksville Compressor Station Maintenance
Notice Text:
Marksville Deliveries Scheduling Group
Gas Day 5/11:
Capacity could be impacted by as much as 100,000 dth/d for the duration of the maintenance.
Gas Day 5/12 - 5/16:
Capacity could be impacted by as much as 250,000 dth/d for the duration of the maintenance. This
maintenance has the potential to impact all services, including Primary Firm Serivce.
Demand charge credits will not be issued during the maintenance period unless Primary Firm Service is
scheduled down during the Timely Nomination Cycle. Any demand charge credits will be calculated pursuant
to Section 6.25 of the General Terms and Conditions of Gulf South`s NGA Gas Tariff.
If you have any questions, please contact your customer service representative.