September 16, 2024

MLV 525 and MLV 526 Maintenance - Update 1

Kinetica Energy Express continue to work on the pipeline maintenance near MLV 525 and MLV 526. Due
to Hurricane Francine, there is slight delay, and the maintenance is estimated to be completed by
October 3, 2024.

Any production East of MLV 526 will have to be delivered to Venice delivery point, meter 020568. Any
production West of MLV 525 cannot be delivered to Venice delivery point, meter 020568. Available
delivery points West are Discovery, meter 021032 and Harvest Egan Gap, 024016.

West of MLV 525

East of MLV 526

Meter

Description

Meter

Description

10932

SS 154 E

10428

MP Blk 35 Dehy Halter ISL

11180

SS 198 H

10516

S Pass Blk 24 Dehy

11182

SS 182 C

10665

WD Blk Dehy 2

11210

SMI 27 A

12438

Snow Well

11691

SS 181 B

12516

Venice Interconnect

11692

SM ISL 106 A

12812

Longhorn Medusa SP 55A

11802

SS 198 J

14003

Hilcorp Homeplace

12428

S M I 72

10599

Mecom Lk Washington Dehy

12435

S M I 76 P

10839

GI Blk 43 Dehy

12644

SS BLK 110 A

12714

Lake Washington SL 212

12815

Egan A South

12838

E I 224 G: RIP 523M 8101

12881

VR 229A

14007

SMI 71: RIP 523M-135

14011

SS 182C #2 RIP 523M-2911

14015

SMI 58G Dehy

14017

VR 78

18003

Pecan Island Station 600

18036

SMI 99

10442

TIMBALIER BAY DEHY

10641

LAPEYROUSE PLANT DEHY

10668

GI BLK 47 DEHY

10688

LAKE RACCOURCI DEHY

12308

S TIM BLK 23

12374

GRAND ISLE DEHY 1

12650

T-Discovery

For questions regarding facilities or operations, please contact Blake Arnold at (281) 702-6377.

For scheduling questions, please contact the Scheduling team at Scheduling@Kineticallc.com.

Customers are strongly advised to monitor the EBB for updates.

September 16, 2024
MLV 525 and MLV 526 Maintenance - Update 1
Kinetica Energy Express continue to work on the pipeline maintenance near MLV 525 and MLV 526. Due
to Hurricane Francine, there is slight delay, and the maintenance is estimated to be completed by
October 3, 2024.
Any production East of MLV 526 will have to be delivered to Venice delivery point, meter 020568. Any
production West of MLV 525 cannot be delivered to Venice delivery point, meter 020568. Available
delivery points West are Discovery, meter 021032 and Harvest Egan Gap, 024016.


West of MLV 525





East of MLV 526

Meter
Description

Meter
Description
10932
SS 154 E

10428
MP Blk 35 Dehy Halter ISL
11180
SS 198 H

10516
S Pass Blk 24 Dehy
11182
SS 182 C

10665
WD Blk Dehy 2
11210
SMI 27 A

12438
Snow Well
11691
SS 181 B

12516
Venice Interconnect
11692
SM ISL 106 A

12812
Longhorn Medusa SP 55A
11802
SS 198 J

14003
Hilcorp Homeplace
12428
S M I 72

10599
Mecom Lk Washington Dehy
12435
S M I 76 P

10839
GI Blk 43 Dehy
12644
SS BLK 110 A

12714
Lake Washington SL 212
12815
Egan A South



12838
E I 224 G: RIP 523M 8101



12881
VR 229A



14007
SMI 71: RIP 523M-135



14011
SS 182C #2 RIP 523M-2911



14015
SMI 58G Dehy



14017
VR 78



18003
Pecan Island Station 600



18036
SMI 99



10442
TIMBALIER BAY DEHY



10641
LAPEYROUSE PLANT DEHY



10668
GI BLK 47 DEHY



10688
LAKE RACCOURCI DEHY



12308
S TIM BLK 23



12374
GRAND ISLE DEHY 1



12650
T-Discovery











For questions regarding facilities or operations, please contact Blake Arnold at (281) 702-6377.
For scheduling questions, please contact the Scheduling team at Scheduling@Kineticallc.com.
Customers are strongly advised to monitor the EBB for updates.