Type Posted Effective End Identifier Status Subject Response
Capacity Constraint 10/15/24 10/15/24 01/15/25 1537 MSPL – MS101521-CANA-R Location Off Rate Effective October 15, 2024
Capacity Constraint 09/30/24 09/30/24 12/30/24 1530 MSPL – MS101753-ENABLE-R Location Off Rate – LIFTED Effective September 30, 2024
Capacity Constraint 09/30/24 09/30/24 12/30/24 1529 MSPL – MS101521-CANA-R Location Off Rate – LIFTED Effective September 30, 2024
Planned Service Outage 09/27/24 09/27/24 10/31/24 1527 MSPL 2024 Planned Outage and Maintenance Summary – Tatums Maintenance Complete – 9.27.24
Capacity Constraint 09/24/24 09/24/24 12/24/24 1523 MSPL – MS101753-ENABLE-R Location Off Rate Effective September 24, 2024
Capacity Constraint 09/20/24 09/20/24 12/20/24 1522 MSPL – MS101521-CANA-R Location Off Rate Effective September 20, 2024
Force Majeure 09/20/24 09/20/24 12/20/24 1521 MSPL Force Majeure – Pipeline Integrity Remediation – LIFTED – Effective 09.20.2024
Planned Service Outage 09/18/24 09/18/24 12/18/24 1515 Subject: MSPL 2024 Planned Outage and Maintenance Summary – 9.18.24
Force Majeure 09/13/24 09/13/24 12/17/24 1514 MSPL Force Majeure – Pipeline Integrity Remediation – Effective 09.17.2024
Capacity Constraint 09/09/24 09/09/24 10/30/24 1507 MS101521-CANA-R Location Off Rate – LIFTED Effective September 9, 2024
Capacity Constraint 09/09/24 09/09/24 10/31/24 1506 MSPL – MS100011-CHISHOLM-R Location Off Rate – LIFTED Effective September 9, 2024
Capacity Constraint 09/04/24 09/04/24 12/04/24 1501 MSPL – MS101521-CANA-R Location Off Rate Effective September 4, 2024
Capacity Constraint 09/04/24 09/04/24 12/04/24 1500 MSPL – MS100011-CHISHOLM-R Location Off Rate Effective September 4, 2024
Capacity Constraint 08/29/24 08/29/24 11/29/24 1495 MSPL – MS104751-IRON HORSE-R Location Off Rate – LIFTED Effective 8.29.24
Capacity Constraint 08/28/24 08/28/24 11/28/24 1490 MSPL – MS104751-IRON HORSE-R Location Off Rate Effective August 28, 2024
Capacity Constraint 08/28/24 08/28/24 11/28/24 1489 MSPL - MS100011-CHISHOLM-R Location Off Rate - LIFTED Effective August 28, 2024
Capacity Constraint 08/26/24 08/26/24 11/26/24 1487 MSPL - MS101521-CANA-R Location Off Rate - LIFTED Effective August 26, 2024
Capacity Constraint 08/21/24 08/21/24 11/21/24 1484 MSPL – MS101753-ENABLE-R – Gas Quality Issue-RESOLVED- Effective August 21, 2024
Capacity Constraint 08/19/24 08/19/24 11/19/24 1483 MSPL – MS100011-CHISHOLM-R Location Off Rate Effective August 19, 2024
Gas Quality 08/15/24 08/15/24 11/15/24 1480 MSPL – MS101753-Enable-R Gas Quality Issue Effective August 15, 2024
Weather Alert 08/15/24 08/15/24 11/15/24 1479 MSPL - Weather Alert and Gas Quality for All Locations Effective August 15, 2024 Until Further Notice
Capacity Constraint 08/12/24 08/12/24 11/12/24 1478 MSPL – MS101521-CANA-R Location Off Rate Effective August 12, 2024
Planned Service Outage 07/29/24 07/29/24 10/31/24 1469 MSPL 2024 Planned Outage and Maintenance Summary – 7.29.24
Capacity Constraint 07/29/24 07/29/24 10/29/24 1468 MSPL – MS101521-CANA-R Location Off Rate Effective July 29, 2024
Computer System Status 08/26/23 08/26/23 11/01/23 1155 MSPL Quorum Database/Server Issues – RESOLVED - 8.26.23