Nordegg Compressor Station Outage Update

Notice Text

Update:

 

The Nordegg compressor station outage restriction will be lifted effective May 15, 2015 at 20:00 MST.

Upon completion of the Nordegg compressor station maintenance, the restricted area Upstream of James River will return to 20% of IT-R and IT-S allowable.

 

The area of impact will remain consistent with the Upstream of James River restriction which includes NGTL Segments 1,2,3,4,5,7,8,9 and 26.

Locations that are excluded are all ATCO receipt locations in Segment 9, & Crammond (#1686), Ricinus (#1135), Ricinus West (#1437) and Strachan (#1115) meter stations.

 

 

An IT receipt restriction is required on NGTL to facilitate planned maintenance at Nordegg compressor station.

Allowable receipts will be limited to 100% of Firm Service Receipts effective Monday May 11 2015 at 08:00 MST with an expected end date of Friday May 15, 2015 at 20:00 MST.

The area of impact will be consistent with the Upstream of James River restriction with includes NGTL Segments 1, 2, 3, 4, 5, 7, 8, 9 and 26

Locations that are excluded from this restriction are all Atco receipt locations in Segment 9, & Crammond (#1686), Ricinus (#1135), Ricinus West (#1437) and Strachan (#1115) meter stations.

All reasonable efforts are being taken to maximize the receipt capability.

 



Notice Type
Other

Effective Start Date Time
05/15/2015 2:00 pm

Subject
Nordegg Compressor Station Outage Update

Notice Text

Update:

 

The Nordegg compressor station outage restriction will be lifted effective May 15, 2015 at 20:00 MST.

Upon completion of the Nordegg compressor station maintenance, the restricted area Upstream of James River will return to 20% of IT-R and IT-S allowable.

 

The area of impact will remain consistent with the Upstream of James River restriction which includes NGTL Segments 1,2,3,4,5,7,8,9 and 26.

Locations that are excluded are all ATCO receipt locations in Segment 9, & Crammond (#1686), Ricinus (#1135), Ricinus West (#1437) and Strachan (#1115) meter stations.

 

 

An IT receipt restriction is required on NGTL to facilitate planned maintenance at Nordegg compressor station.

Allowable receipts will be limited to 100% of Firm Service Receipts effective Monday May 11 2015 at 08:00 MST with an expected end date of Friday May 15, 2015 at 20:00 MST.

The area of impact will be consistent with the Upstream of James River restriction with includes NGTL Segments 1, 2, 3, 4, 5, 7, 8, 9 and 26

Locations that are excluded from this restriction are all Atco receipt locations in Segment 9, & Crammond (#1686), Ricinus (#1135), Ricinus West (#1437) and Strachan (#1115) meter stations.