NGTL Notice 3026036010
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
08/13/2015 2:00 pm
Subject
Swarts Creek Compressor Planned Maintenance
Notice Text
A FT receipt restriction is
required on NGTL to facilitate planned maintenance at Swartz Creek compressor
station.
Allowable receipts will be limited to 90% of Firm Service
Receipts effective Monday August 17, 2015 at 08:00 MST with an expected end date
of Thursday August 20, 2015 at 08:00 MST.
The area of impact will be consistent with the Upstream of James River restriction with includes NGTL Segments 1, 2, 3, 4, 5, 7, 8, 9 and 26.
Locations that are excluded from this restriction are all
ATCO receipt locations in Segment 9, Crammond
(#1686) & Chip Lake (#5406) meter stations.
All reasonable efforts are being taken to maximize the receipt capability.
Capacity Constraint
Effective Start Date Time
08/13/2015 2:00 pm
Subject
Swarts Creek Compressor Planned Maintenance
Notice Text
A FT receipt restriction is
required on NGTL to facilitate planned maintenance at Swartz Creek compressor
station.
Allowable receipts will be limited to 90% of Firm Service
Receipts effective Monday August 17, 2015 at 08:00 MST with an expected end date
of Thursday August 20, 2015 at 08:00 MST.
The area of impact will be consistent with the Upstream of James River restriction with includes NGTL Segments 1, 2, 3, 4, 5, 7, 8, 9 and 26.
Locations that are excluded from this restriction are all
ATCO receipt locations in Segment 9, Crammond
(#1686) & Chip Lake (#5406) meter stations.
All reasonable efforts are being taken to maximize the receipt capability.