NGTL Notice 3094221010
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
08/29/2016 2:00 pm
Subject
East Gate Restriction Aug 30, 2016
Notice Text
NGTL Eastern
Gate (EGAT) delivery area gas demand exceeds the current NGTL delivery
capability. As a result, an EGAT delivery area Interruptible Delivery
service (IT-D) restriction will be implemented for gas day Aug 30, 2016 at 08:00 MST.
On Aug 29, 2016,
following the Evening Cycle capacity allocation, a NrG notice will be issued
communicating the IT-D allowable percentage for gas day Aug 30, 2016 at 08:00 MST.
The delivery allowable is reviewed daily and may be adjusted at any time based
on System operation and supply demand distribution.
Eastern
Gate delivery area includes NGTL
Segments 10-20, 22, 23, 28 and partial 21.
Partial
Segment 21 includes the following
delivery locations.
21.WGAT
Carseland Cogen Sales APS - M/S # 31017
21.WGAT
Garrington Sales - M/S # 3128
21.WGAT
Shepard Energy Centre Sales APS - M/S # 31127
The
following interconnect delivery locations are within the Eastern Gate delivery
area.
14.COLD
Cold Lake
Border- M/S # 1417
16.ELAT
Unity Border - M/S # 1250
17.ALEG
Carbon Interconnect - M/S # 3866
18.BLEG
Crossfield East Interconnect - M/S # 3897
18.BLEG
Severn Creek Interconnect - M/S # 3862
18.BLEG
Chancellor Interconnect - M/S # 3907
19.EGAT
Aeco Interconnect - M/S # 3880
19.EGAT
Empress Border - M/S # 1249
19.EGAT
Mcneill Border - M/S # 6404
28.EDM
Warwick Southeast Storage - M/S # 3948
A number
of resources are available for customers looking for capacity information and
can be accessed online at the following locations:
Customer
Express: http://www.transcanada.com/customerexpress/ngtl.html
NGTL
Tariff - General Terms and Conditions, Section 11.4 - Interruptions and
Curtailments: http://www.transcanada.com/customerexpress/docs/ab_regulatory_tariff/General_Terms_and_Conditions-2015.pdf
Please see
the following link for specific instructions regarding the EGAT (NGTL /
Foothills Zone 9 / TCPL): http://www.transcanada.com/customerexpress/docs/ab_nominations_procedures/EGATE_Restriction_Procedure__Feb_27_2014.pdf
Customers are also encouraged to
review procedures applying to delivery service restrictions, including the
process to manage over-consumption, which are available through the following
hyperlink:
http://www.transcanada.com/customerexpress/3174.html
All
reasonable efforts are made to optimize outage scheduling, minimize outage
duration, and maximize operational capability. Refer to the Short Term
Operational Plan for near term outage plans. Short
Term Operational Plan: |
http://www.transcanada.com/customerexpress/abshorttermopsplan.html
Capacity Constraint
Effective Start Date Time
08/29/2016 2:00 pm
Subject
East Gate Restriction Aug 30, 2016
Notice Text
NGTL Eastern
Gate (EGAT) delivery area gas demand exceeds the current NGTL delivery
capability. As a result, an EGAT delivery area Interruptible Delivery
service (IT-D) restriction will be implemented for gas day Aug 30, 2016 at 08:00 MST.
On Aug 29, 2016,
following the Evening Cycle capacity allocation, a NrG notice will be issued
communicating the IT-D allowable percentage for gas day Aug 30, 2016 at 08:00 MST.
The delivery allowable is reviewed daily and may be adjusted at any time based
on System operation and supply demand distribution.
Eastern
Gate delivery area includes NGTL
Segments 10-20, 22, 23, 28 and partial 21.
Partial
Segment 21 includes the following
delivery locations.
21.WGAT
Carseland Cogen Sales APS - M/S # 31017
21.WGAT
Garrington Sales - M/S # 3128
21.WGAT
Shepard Energy Centre Sales APS - M/S # 31127
The
following interconnect delivery locations are within the Eastern Gate delivery
area.
14.COLD
Cold Lake
Border- M/S # 1417
16.ELAT
Unity Border - M/S # 1250
17.ALEG
Carbon Interconnect - M/S # 3866
18.BLEG
Crossfield East Interconnect - M/S # 3897
18.BLEG
Severn Creek Interconnect - M/S # 3862
18.BLEG
Chancellor Interconnect - M/S # 3907
19.EGAT
Aeco Interconnect - M/S # 3880
19.EGAT
Empress Border - M/S # 1249
19.EGAT
Mcneill Border - M/S # 6404
28.EDM
Warwick Southeast Storage - M/S # 3948
A number
of resources are available for customers looking for capacity information and
can be accessed online at the following locations:
Customer
Express: http://www.transcanada.com/customerexpress/ngtl.html
NGTL
Tariff - General Terms and Conditions, Section 11.4 - Interruptions and
Curtailments: http://www.transcanada.com/customerexpress/docs/ab_regulatory_tariff/General_Terms_and_Conditions-2015.pdf
Please see
the following link for specific instructions regarding the EGAT (NGTL /
Foothills Zone 9 / TCPL): http://www.transcanada.com/customerexpress/docs/ab_nominations_procedures/EGATE_Restriction_Procedure__Feb_27_2014.pdf
Customers are also encouraged to
review procedures applying to delivery service restrictions, including the
process to manage over-consumption, which are available through the following
hyperlink:
http://www.transcanada.com/customerexpress/3174.html
All
reasonable efforts are made to optimize outage scheduling, minimize outage
duration, and maximize operational capability. Refer to the Short Term
Operational Plan for near term outage plans. Short
Term Operational Plan: |
http://www.transcanada.com/customerexpress/abshorttermopsplan.html