NGTL Notice 3124747010
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
02/07/2017 3:00 pm
Subject
Winchell Lake Compressor Unplanned Outage Update
Notice Text
The unplanned maintenance at Winchell Lake
compressor station has concluded. The delivery capability at the
Alberta/B.C. border for Feb 7th, 2017 at 13:00 MST will be revised to 62 e6m3/d. Please note the Short Term Operational
Plan (STOP) will be updated later today.
All reasonable efforts are made to optimize outage
scheduling, minimize outage duration, and maximize operational capability.
Refer to the Short Term Operational Plan for near term outage plans and the
Monthly Outage Forecast for longer term outage plans.
Short Term Operational Plan: http://www.transcanada.com/customerexpress/abshorttermopsplan.html
Monthly Outage Forecast: http://www.transcanada.com/customerexpress/2880.html
As a result of unplanned maintenance
at Winchell Lake Compressor Station, effective Tuesday, February 7th,
2017 at 08:00 MST, the delivery capability at the Alberta/B.C. border
will be limited to 50 e6m3/d. These allowable service
levels are expected to remain in effect until further notice.
All
reasonable efforts are made to optimize outage scheduling, minimize outage
duration, and maximize operational capability. Refer to the Short Term
Operational Plan for near term outage plans and the Monthly Outage Forecast
for longer term outage plans. Short
Term Operational Plan: http://www.transcanada.com/customerexpress/abshorttermopsplan.html |
Monthly Outage Forecast: http://www.transcanada.com/customerexpress/2880.html
Capacity Constraint
Effective Start Date Time
02/07/2017 3:00 pm
Subject
Winchell Lake Compressor Unplanned Outage Update
Notice Text
The unplanned maintenance at Winchell Lake
compressor station has concluded. The delivery capability at the
Alberta/B.C. border for Feb 7th, 2017 at 13:00 MST will be revised to 62 e6m3/d. Please note the Short Term Operational
Plan (STOP) will be updated later today.
All reasonable efforts are made to optimize outage
scheduling, minimize outage duration, and maximize operational capability.
Refer to the Short Term Operational Plan for near term outage plans and the
Monthly Outage Forecast for longer term outage plans.
Short Term Operational Plan: http://www.transcanada.com/customerexpress/abshorttermopsplan.html
Monthly Outage Forecast: http://www.transcanada.com/customerexpress/2880.html
As a result of unplanned maintenance
at Winchell Lake Compressor Station, effective Tuesday, February 7th,
2017 at 08:00 MST, the delivery capability at the Alberta/B.C. border
will be limited to 50 e6m3/d. These allowable service
levels are expected to remain in effect until further notice.
All
reasonable efforts are made to optimize outage scheduling, minimize outage
duration, and maximize operational capability. Refer to the Short Term
Operational Plan for near term outage plans and the Monthly Outage Forecast
for longer term outage plans. Short
Term Operational Plan: http://www.transcanada.com/customerexpress/abshorttermopsplan.html |
Monthly Outage Forecast: http://www.transcanada.com/customerexpress/2880.html