NGTL Notice 3374723473

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice Type
Capacity Constraint

Effective Start Date Time
10/28/2024 1:00 pm

Subject
NGTL Service (USJR IT-R)

Notice Text

 NGTL Service (USJR IT-R)

 

USJR: Planned maintenance at the Goodfish Compressor Station (19280392) is complete and maintenance at the Meikle River D5 Compressor Station (19358504) is ongoing. With current system operation and supply distribution, effective October 29, 2024 at 08:00 MST, service allowable for segments 2, 3, 4, and partial 7 (Upstream Latornell) will transition from 0% IT-R and 100% FT-R to 100% IT-R and 100% FT-R until further notice.

 

WGAT: N/A

 

EGAT: N/A

 

Local Area/Location: N/A

 

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

 Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19280392

Oct. 21, 2024

Oct. 25, 2024

 Goodfish

Compressor Maintenance

Planned

USJR

19358504

Oct. 14, 2024

Oct. 29, 2024

 Meikle River D

Compressor Maintenance

Planned

USJR

 

Upstream James River Receipt Area

Effective:

October 17, 2024 at 08:00 MST

IT Allowable: 0%

IT-R

 IT-S (receipt)

 

 

Expected End:

October 29, 2024 at 08:00 MST

FT Allowable: 100%

FT-R

FT-P

 

 

 

Interconnects:

  Aitken Creek, Groundbirch East, Gordondale

Segments:

 Segments 2, 3, 4, and partial 7 (Upstream of Latornell)

Effective:

October 29, 2024 at 08:00 MST

IT Allowable: 100%

IT-R

 IT-S (receipt)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-R

FT-P

 

 

 

Interconnects:

  Aitken Creek, Big Eddy, Groundbirch East, Gordondale, January Creek

Segments:

2, 3, 4, 5, 7, partial 8, and partial 9

 

West Gate Delivery Area

Effective:

July 25, 2024 at 08:00 MST

IT Allowable: 100%

IT-D

 

 

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Alberta-B.C. Border and Alberta Montana Border

Segments:

 22 and partial 21 (Greater WGAT)

 

East Gate Delivery Area

Effective:

July 10, 2024 at 08:00 MST

IT Allowable: 100%

IT-D

IT-S (delivery)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

Aeco C, Carbon, Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Cold Lake, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT)

 

 

Local Area/Location

N/A

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.

NGTL System - Segment Codes & Project Areas Map NGTL System - Operational Areas Map



Notice Type
Capacity Constraint

Effective Start Date Time
10/28/2024 1:00 pm

Subject
NGTL Service (USJR IT-R)

Notice Text

 NGTL Service (USJR IT-R)

 

USJR: Planned maintenance at the Goodfish Compressor Station (19280392) is complete and maintenance at the Meikle River D5 Compressor Station (19358504) is ongoing. With current system operation and supply distribution, effective October 29, 2024 at 08:00 MST, service allowable for segments 2, 3, 4, and partial 7 (Upstream Latornell) will transition from 0% IT-R and 100% FT-R to 100% IT-R and 100% FT-R until further notice.

 

WGAT: N/A

 

EGAT: N/A

 

Local Area/Location: N/A

 

New Information

Updated Information

 

Current and upcoming outages

Outage ID

Start

End

 Facility/Outage Name

Facility Type/Scope

Outage Type

Area of Impact

19280392

Oct. 21, 2024

Oct. 25, 2024

 Goodfish

Compressor Maintenance

Planned

USJR

19358504

Oct. 14, 2024

Oct. 29, 2024

 Meikle River D

Compressor Maintenance

Planned

USJR

 

Upstream James River Receipt Area

Effective:

October 17, 2024 at 08:00 MST

IT Allowable: 0%

IT-R

 IT-S (receipt)

 

 

Expected End:

October 29, 2024 at 08:00 MST

FT Allowable: 100%

FT-R

FT-P

 

 

 

Interconnects:

  Aitken Creek, Groundbirch East, Gordondale

Segments:

 Segments 2, 3, 4, and partial 7 (Upstream of Latornell)

Effective:

October 29, 2024 at 08:00 MST

IT Allowable: 100%

IT-R

 IT-S (receipt)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-R

FT-P

 

 

 

Interconnects:

  Aitken Creek, Big Eddy, Groundbirch East, Gordondale, January Creek

Segments:

2, 3, 4, 5, 7, partial 8, and partial 9

 

West Gate Delivery Area

Effective:

July 25, 2024 at 08:00 MST

IT Allowable: 100%

IT-D

 

 

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

  Alberta-B.C. Border and Alberta Montana Border

Segments:

 22 and partial 21 (Greater WGAT)

 

East Gate Delivery Area

Effective:

July 10, 2024 at 08:00 MST

IT Allowable: 100%

IT-D

IT-S (delivery)

 

 

Expected End:

Until further notice

FT Allowable: 100%

FT-P

FT-D1

FT-D2

STFT

 

Interconnects:

Aeco C, Carbon, Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Cold Lake, Warwick SE

Segments:

6, 10, 11, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT)

 

 

Local Area/Location

N/A

 

If there is an overlap between Local Area/Location and Upstream James River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then the lower IT Allowable and FT Allowable will be in effect. The details in this bulletin supersede any previously published information and will be reflected and maintained in the next release of the Daily Operating Plan.

NGTL System - Segment Codes & Project Areas Map NGTL System - Operational Areas Map