NGTL Notice 3374723602
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
02/05/2025 7:24 pm
Subject
NGTL Service (USJR IT-R, NEDA FT-D)
Notice Text
NGTL Service (USJR IT-R, NEDA FT-D)
USJR: The planned pipeline modification work on the NPS 36 Grande Prairie Mainline (19914174) is ongoing and
progressing well. Based on current supply
and demand distribution, service allowable for segments 2, 3, 4, 5, 7, partial
8, and partial 9 (Greater USJR) will transition from 0% IT-R and 100% FT-R to
100% IT-R and 100% FT-R effective February 5, 2025 at 17:00 MST until further
notice.
WGAT: N/A
EGAT: Due to unplanned maintenance on the Paul Lake Compressor Station (19995345),
service allowable in Segments 6, 10, 11,
13, 14, 15, 16, 17, 23, 24, partial 28 (NEDA) will transition from 100% IT-D and 100% FT-D to 0% IT-D and 80%
FT-D effective February 5, 2025 at 17:00 MST until further notice. Technicians
are on site, actively troubleshooting, and parts are en
route to site. At this time, return to service is expected to be within 24-48
hours. For the purposes of the DOP that will be published today, a placeholder
end date of February 7, 2025 will be used until more information is known. An
update will be provided at 7:30AM tomorrow morning.
Local Area/Location: N/A
New
Information |
Updated
Information |
Current
and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage
Name |
Facility Type/Scope |
Outage
Type |
Area
of Impact |
19914174 |
Jan. 30, 2025 |
Feb. 10, 2025 |
NPS 36 Grande Prairie Mainline |
Pipeline Modification |
Planned |
USJR |
19995345 |
Feb. 5, 2025 |
TBD |
Paul Lake |
Compressor Station Maintenance |
Unplanned |
NEDA |
Upstream
James River Receipt Area |
|||||||
Effective: |
January 30, 2025 at 08:00 MST |
IT
Allowable: 0% |
IT-R |
IT-S (receipt) |
|
|
|
Expected
End: |
February 5, 2025 at 17:00
MST |
FT
Allowable: 100% |
FT-R |
FT-P |
|
|
|
Interconnects: |
Aitken Creek, Big Eddy, Groundbirch East, Gordondale,
January Creek |
||||||
Segments: |
|||||||
Effective: |
February 5, 2025 at 17:00
MST |
IT Allowable: 100% |
IT-R |
IT-S (receipt) |
|
|
|
Expected End: |
Until further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
|
|
Interconnects: |
Aitken
Creek, Big Eddy, Groundbirch East, Gordondale, January Creek |
||||||
Segments: |
West
Gate Delivery Area |
|||||||
Effective: |
July 25, 2024 at 08:00 MST |
IT
Allowable: 100% |
IT-D |
|
|
|
|
Expected
End: |
Until further notice |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Alberta-B.C. Border and Alberta
Montana Border |
||||||
Segments: |
East
Gate Delivery Area |
|||||||
Effective: |
|
IT
Allowable: 100% |
IT-D |
IT-S (delivery) |
|
|
|
Expected
End: |
February 5, 2025 at |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Aeco C, Carbon,
Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Cold
Lake, Warwick SE |
||||||
Segments: |
6, 10, 11, 13, 14, 15, 16, 17,
18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT) |
||||||
Effective: |
|
IT
Allowable: 0% |
IT-D |
IT-S (delivery) |
|
|
|
Expected
End: |
Until further notice |
FT
Allowable: 80% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Unity, Cold Lake, Warwick
SE |
||||||
Segments: |
6, 10,
11, 13, 14, 15, 16, 17, 23, 24, and partial 28 (NEDA) |
N/A |
If there is an overlap between Local Area/Location and Upstream James
River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then
the lower IT Allowable and FT Allowable will be in
effect. The details in this bulletin supersede any previously published
information and will be reflected
and maintained in the next release of the Daily Operating Plan.
NGTL System - Segment Codes &
Project Areas Map NGTL System - Operational Areas Map
Capacity Constraint
Effective Start Date Time
02/05/2025 7:24 pm
Subject
NGTL Service (USJR IT-R, NEDA FT-D)
Notice Text
NGTL Service (USJR IT-R, NEDA FT-D)
USJR: The planned pipeline modification work on the NPS 36 Grande Prairie Mainline (19914174) is ongoing and
progressing well. Based on current supply
and demand distribution, service allowable for segments 2, 3, 4, 5, 7, partial
8, and partial 9 (Greater USJR) will transition from 0% IT-R and 100% FT-R to
100% IT-R and 100% FT-R effective February 5, 2025 at 17:00 MST until further
notice.
WGAT: N/A
EGAT: Due to unplanned maintenance on the Paul Lake Compressor Station (19995345),
service allowable in Segments 6, 10, 11,
13, 14, 15, 16, 17, 23, 24, partial 28 (NEDA) will transition from 100% IT-D and 100% FT-D to 0% IT-D and 80%
FT-D effective February 5, 2025 at 17:00 MST until further notice. Technicians
are on site, actively troubleshooting, and parts are en
route to site. At this time, return to service is expected to be within 24-48
hours. For the purposes of the DOP that will be published today, a placeholder
end date of February 7, 2025 will be used until more information is known. An
update will be provided at 7:30AM tomorrow morning.
Local Area/Location: N/A
New
Information |
Updated
Information |
Current
and upcoming outages |
||||||
Outage ID |
Start |
End |
Facility/Outage
Name |
Facility Type/Scope |
Outage
Type |
Area
of Impact |
19914174 |
Jan. 30, 2025 |
Feb. 10, 2025 |
NPS 36 Grande Prairie Mainline |
Pipeline Modification |
Planned |
USJR |
19995345 |
Feb. 5, 2025 |
TBD |
Paul Lake |
Compressor Station Maintenance |
Unplanned |
NEDA |
Upstream
James River Receipt Area |
|||||||
Effective: |
January 30, 2025 at 08:00 MST |
IT
Allowable: 0% |
IT-R |
IT-S (receipt) |
|
|
|
Expected
End: |
February 5, 2025 at 17:00
MST |
FT
Allowable: 100% |
FT-R |
FT-P |
|
|
|
Interconnects: |
Aitken Creek, Big Eddy, Groundbirch East, Gordondale,
January Creek |
||||||
Segments: |
|||||||
Effective: |
February 5, 2025 at 17:00
MST |
IT Allowable: 100% |
IT-R |
IT-S (receipt) |
|
|
|
Expected End: |
Until further notice |
FT Allowable: 100% |
FT-R |
FT-P |
|
|
|
Interconnects: |
Aitken
Creek, Big Eddy, Groundbirch East, Gordondale, January Creek |
||||||
Segments: |
West
Gate Delivery Area |
|||||||
Effective: |
July 25, 2024 at 08:00 MST |
IT
Allowable: 100% |
IT-D |
|
|
|
|
Expected
End: |
Until further notice |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Alberta-B.C. Border and Alberta
Montana Border |
||||||
Segments: |
East
Gate Delivery Area |
|||||||
Effective: |
|
IT
Allowable: 100% |
IT-D |
IT-S (delivery) |
|
|
|
Expected
End: |
February 5, 2025 at |
FT
Allowable: 100% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Aeco C, Carbon,
Chancellor, Crossfield East #2, Severn Creek, Empress, McNeil, Unity, Cold
Lake, Warwick SE |
||||||
Segments: |
6, 10, 11, 13, 14, 15, 16, 17,
18, 19, 20, 23, 24, partial 21 and partial 28 (Greater EGAT) |
||||||
Effective: |
|
IT
Allowable: 0% |
IT-D |
IT-S (delivery) |
|
|
|
Expected
End: |
Until further notice |
FT
Allowable: 80% |
FT-P |
FT-D1 |
FT-D2 |
STFT |
|
Interconnects: |
Unity, Cold Lake, Warwick
SE |
||||||
Segments: |
6, 10,
11, 13, 14, 15, 16, 17, 23, 24, and partial 28 (NEDA) |
N/A |
If there is an overlap between Local Area/Location and Upstream James
River Receipt Area, West Gate Delivery Area, or East Gate Delivery Area, then
the lower IT Allowable and FT Allowable will be in
effect. The details in this bulletin supersede any previously published
information and will be reflected
and maintained in the next release of the Daily Operating Plan.
NGTL System - Segment Codes &
Project Areas Map NGTL System - Operational Areas Map