Tennessee Gas Pipeline Notice 391895

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  08/09/2024 7:57:38PM Notice End Date/Time:  08/10/2024 9:00:00am
Post Date/Time:  8/9/2024 7:57:38 PM Notice ID: 391895
Reqrd Rsp:  1 Rsp Date:  08/09/2024
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 08-09-2024 ID3
Notice Text:

Effective Intraday 3 Cycle (22:00) for the gas day of Friday, August 09, 2024 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

METER RESTRICTIONS

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

SEGMENT RESTRICTIONS

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to force majeure at STA 860; 10,000 Dths

·         MLV 524 (Segment 524 FH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,990 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases due to operational concerns; 9,891 Dths

·         STA 204 (Segment 204 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 17,279 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 600 Dths

·         Z5hc North (Segment 299 FH) - through approx 52% of SOP increases due to nominations in excess of operational capacity; 36,401 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

 

Tennessee will not accept nominations for FSAO injections at all storage fields.

 

Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  08/09/2024 7:57:38PM Notice End Date/Time:  08/10/2024 9:00:00am
Post Date/Time:  8/9/2024 7:57:38 PM Notice ID: 391895
Reqrd Rsp:  1 Rsp Date:  08/09/2024
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 08-09-2024 ID3
Notice Text:

Effective Intraday 3 Cycle (22:00) for the gas day of Friday, August 09, 2024 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

METER RESTRICTIONS

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

SEGMENT RESTRICTIONS

·         STA 860 (Segment 860 BH) - through 100% of SOP increases due to force majeure at STA 860; 10,000 Dths

·         MLV 524 (Segment 524 FH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,990 Dths

·         STA 110 South (Segment 187 BH) - through 100% of SOP increases due to operational concerns; 9,891 Dths

·         STA 204 (Segment 204 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 17,279 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 600 Dths

·         Z5hc North (Segment 299 FH) - through approx 52% of SOP increases due to nominations in excess of operational capacity; 36,401 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field. 

 

Tennessee will not accept nominations for FSAO injections at all storage fields.

 

Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.

 

Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.