Tennessee Gas Pipeline Notice 393479

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  01/19/2025 8:14:31PM Notice End Date/Time:  01/20/2025 9:00:00am
Post Date/Time:  1/19/2025 8:14:31 PM Notice ID: 393479
Reqrd Rsp:  1 Rsp Date:  01/19/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 01-20-2025 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Monday, January 20, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 2 SYSTEM WIDE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

 

METER RESTRICTIONS

·         TGP/SNG Bear Creek Injection Bienvi Receipt Meter (Pin 405367) - through 100% of SOP increases due to operational concerns; 49,565 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 44,033 Dths

·         STA 523 Cocodrie Lateral (Segment 959 BH) - through 100% of IT increases due to nominations in excess of operational capacity; 4,138 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 257,895 Dths

·         MLV 314 East (Segment 314 BH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 89,198 Dths

·         STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 576,461 Dths

·         MLV 355 (Segment 355Fh) - through 100% of SOP increases due to operational concerns; 8,004 Dths

·         STA 224 (Segment 224 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,401 Dths

·         Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 243,904 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 251,611 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 40,928 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

Nominations for Authorized Overrun Withdrawal Services (FS-AO) at the Northern MA (460018) storage field, the Portland MA (460025) storage field, the Portland PA (460020) storage field or the Bear Creek PA (460017) storage field will not be allowed until further notice.  Additionally, customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) only until further notice.

Nominations for Firm Storage Flex Authorized Overrun (FSF-AO) Withdrawal Services under Rate Schedule FS-F at the Pine Prairie Virtual Meter (54628) will not be allowed until further notice.

 

Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice.

 

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals. Additionally, no transfers from IS-MA and IS-PA to FS will be allowed until further notice.

 

No Loans or Park Withdrawals under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.

 

 

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  01/19/2025 8:14:31PM Notice End Date/Time:  01/20/2025 9:00:00am
Post Date/Time:  1/19/2025 8:14:31 PM Notice ID: 393479
Reqrd Rsp:  1 Rsp Date:  01/19/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 01-20-2025 EC
Notice Text:

Effective Evening Cycle (9:00) for the gas day of Monday, January 20, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 2 SYSTEM WIDE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

 

 

 

METER RESTRICTIONS

·         TGP/SNG Bear Creek Injection Bienvi Receipt Meter (Pin 405367) - through 100% of SOP increases due to operational concerns; 49,565 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 69% of SOP increases due to nominations in excess of operational capacity; 44,033 Dths

·         STA 523 Cocodrie Lateral (Segment 959 BH) - through 100% of IT increases due to nominations in excess of operational capacity; 4,138 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 257,895 Dths

·         MLV 314 East (Segment 314 BH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 89,198 Dths

·         STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 576,461 Dths

·         MLV 355 (Segment 355Fh) - through 100% of SOP increases due to operational concerns; 8,004 Dths

·         STA 224 (Segment 224 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,401 Dths

·         Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 243,904 Dths

·         STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 251,611 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 40,928 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

Nominations for Authorized Overrun Withdrawal Services (FS-AO) at the Northern MA (460018) storage field, the Portland MA (460025) storage field, the Portland PA (460020) storage field or the Bear Creek PA (460017) storage field will not be allowed until further notice.  Additionally, customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) only until further notice.

Nominations for Firm Storage Flex Authorized Overrun (FSF-AO) Withdrawal Services under Rate Schedule FS-F at the Pine Prairie Virtual Meter (54628) will not be allowed until further notice.

 

Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice.

 

Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice.  Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals. Additionally, no transfers from IS-MA and IS-PA to FS will be allowed until further notice.

 

No Loans or Park Withdrawals under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.

 

 

 

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.