Tennessee Gas Pipeline Notice 393506
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 01/21/2025 2:26:51PM | Notice End Date/Time: 01/22/2025 9:00:00am |
Post Date/Time: 1/21/2025 2:26:51 PM | Notice ID: 393506 |
Reqrd Rsp: 1 | Rsp Date: 01/21/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 01-22-2025 TIMELY CYCLE |
Effective Timely Cycle (9:00) for the gas day of Wednesday, January 22, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 2 SYSTEM WIDE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TGP/SNG Bear Creek Injection Bienvi Receipt Meter (Pin 405367) - through approx 100 % of SOP due to operational concerns; 65,203 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 66 % of SIPss due to nominations in excess of operational capacity; 151,880 Dths
· IROQUOIS/TGP Shelton Interconnect F Receipt Meter (Pin 412180) - through approx 56 % of IT (through a rate of .1891) due to nominations in excess of operational capacity; 89,628 Dths
· Wright Receipt Meter (Pin 412181) - through approx 53 % of SIPss due to nominations in excess of operational capacity; 196,667 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through approx 5 % of SOP due to nominations in excess of operational capacity; 16,071 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 15,000 Dths
· STA 87 South 800 Line (Segment 860 BH) - through approx 100 % of IT due to nominations in excess of operational capacity; 991 Dths
· STA 860 South 500 Line (Segment 548 BH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 11,866 Dths
· STA 307 (Segment 307 BH) - through approx 60 % of SOP due to nominations in excess of operational capacity; 154,749 Dths
· MLV 314 East (Segment 314 BH) - through approx 53 % of SOP due to nominations in excess of operational capacity; 157,706 Dths
· STA 315 (Segment 315 BH) - through approx 44 % of SOP due to nominations in excess of operational capacity; 180,201 Dths
· STA 321 (Segment 321 FH) - through approx 92 % of SOP due to nominations in excess of operational capacity; 1,004,839 Dths
· STA 325 (Segment 324 FH) - through approx 78 % of SOP due to nominations in excess of operational capacity; 232,094 Dths
· MLV 330 (Segment 324 FH) - through approx 100 % of IT due to nominations in excess of operational capacity; 33,762 Dths
· MLV 336 East (Segment 336 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 40,000 Dths
· MLV 355 (Segment 355FH) - through approx 100 % of SOP due to operational concerns; 4,479 Dths
· STA 224 (Segment 224 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 261,850 Dths
· Z5hc North (Segment 299 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 785,944 Dths
· STA 245 (Segment 245 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 324,112 Dths
· STA 254 (Segment 249 FH) - through approx 88 % of SOP due to nominations in excess of operational capacity; 252,120 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 183,106 Dths
· MLV 265E Cranston Lateral South (Segment 281 FH) - through approx 21 % of SOP due to nominations in excess of operational capacity; 3,945 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Nominations for Authorized Overrun Withdrawal Services (FS-AO) at the Northern MA (460018) storage field, the Portland MA (460025) storage field, the Portland PA (460020) storage field or the Bear Creek PA (460017) storage field will not be allowed until further notice. Additionally, customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) only until further notice.
Nominations for Firm Storage Flex Authorized Overrun (FSF-AO) Withdrawal Services under Rate Schedule FS-F at the Pine Prairie Virtual Meter (54628) will not be allowed until further notice.
Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals. Additionally, no transfers from IS-MA and IS-PA to FS will be allowed until further notice.
No Loans or Park Withdrawals under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 01/21/2025 2:26:51PM | Notice End Date/Time: 01/22/2025 9:00:00am |
Post Date/Time: 1/21/2025 2:26:51 PM | Notice ID: 393506 |
Reqrd Rsp: 1 | Rsp Date: 01/21/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 01-22-2025 TIMELY CYCLE |
Effective Timely Cycle (9:00) for the gas day of Wednesday, January 22, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 2 SYSTEM WIDE FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TGP/SNG Bear Creek Injection Bienvi Receipt Meter (Pin 405367) - through approx 100 % of SOP due to operational concerns; 65,203 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 66 % of SIPss due to nominations in excess of operational capacity; 151,880 Dths
· IROQUOIS/TGP Shelton Interconnect F Receipt Meter (Pin 412180) - through approx 56 % of IT (through a rate of .1891) due to nominations in excess of operational capacity; 89,628 Dths
· Wright Receipt Meter (Pin 412181) - through approx 53 % of SIPss due to nominations in excess of operational capacity; 196,667 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through approx 5 % of SOP due to nominations in excess of operational capacity; 16,071 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 15,000 Dths
· STA 87 South 800 Line (Segment 860 BH) - through approx 100 % of IT due to nominations in excess of operational capacity; 991 Dths
· STA 860 South 500 Line (Segment 548 BH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 11,866 Dths
· STA 307 (Segment 307 BH) - through approx 60 % of SOP due to nominations in excess of operational capacity; 154,749 Dths
· MLV 314 East (Segment 314 BH) - through approx 53 % of SOP due to nominations in excess of operational capacity; 157,706 Dths
· STA 315 (Segment 315 BH) - through approx 44 % of SOP due to nominations in excess of operational capacity; 180,201 Dths
· STA 321 (Segment 321 FH) - through approx 92 % of SOP due to nominations in excess of operational capacity; 1,004,839 Dths
· STA 325 (Segment 324 FH) - through approx 78 % of SOP due to nominations in excess of operational capacity; 232,094 Dths
· MLV 330 (Segment 324 FH) - through approx 100 % of IT due to nominations in excess of operational capacity; 33,762 Dths
· MLV 336 East (Segment 336 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 40,000 Dths
· MLV 355 (Segment 355FH) - through approx 100 % of SOP due to operational concerns; 4,479 Dths
· STA 224 (Segment 224 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 261,850 Dths
· Z5hc North (Segment 299 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 785,944 Dths
· STA 245 (Segment 245 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 324,112 Dths
· STA 254 (Segment 249 FH) - through approx 88 % of SOP due to nominations in excess of operational capacity; 252,120 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 183,106 Dths
· MLV 265E Cranston Lateral South (Segment 281 FH) - through approx 21 % of SOP due to nominations in excess of operational capacity; 3,945 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Nominations for Authorized Overrun Withdrawal Services (FS-AO) at the Northern MA (460018) storage field, the Portland MA (460025) storage field, the Portland PA (460020) storage field or the Bear Creek PA (460017) storage field will not be allowed until further notice. Additionally, customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) only until further notice.
Nominations for Firm Storage Flex Authorized Overrun (FSF-AO) Withdrawal Services under Rate Schedule FS-F at the Pine Prairie Virtual Meter (54628) will not be allowed until further notice.
Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals. Additionally, no transfers from IS-MA and IS-PA to FS will be allowed until further notice.
No Loans or Park Withdrawals under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.