Tennessee Gas Pipeline Notice 394152

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  03/27/2025 3:46:47PM Notice End Date/Time:  03/28/2025 9:00:00am
Post Date/Time:  3/27/2025 3:46:47 PM Notice ID: 394152
Reqrd Rsp:  1 Rsp Date:  03/27/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 03-28-2025 TC REVISED
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Friday, March 28, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

REVISED

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 80,000 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP due to operational concerns; 5,000 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths

·         Atmos KY/TGP Danville Ky Boyle Delivery Meter (Pin 400462) - through approx 3% of SOP due to nominations in excess of operational capacity; 245 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 59% of SIPss due to nominations in excess of operational capacity; 64,863 Dths

SEGMENT RESTRICTIONS

·         STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to emergent repair at STA 40; 10,664 Dths

·         STA 823 (Segment 823 BH) - through 100% of SOP due to nominations in excess of operational capacity; 25,182 Dths

·         STA 834 (Segment 834 BH) - through approx 48% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 70,047 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 69,826 Dths

·         STA 307 (Segment 307 BH) - through approx 84% of SOP due to nominations in excess of operational capacity; 223,563 Dths

·         MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 275,788 Dths

·         STA 315 (Segment 315 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 456,028 Dths

·         STA 321 (Segment 321 FH) - through approx 45% of SOP due to emergent repair at STA 321 UNIT 5B; 370,111 Dths

·         MLV 330 (Segment 324 FH) - through approx 22% of SOP due to nominations in excess of operational capacity; 95,823 Dths

·         MLV 336 East (Segment 336 FH) - through approx 97% of SOP due to nominations in excess of operational capacity; 83,833 Dths

·         Z5hc North (Segment 299 FH) - through approx 90% of SOP due to nominations in excess of operational capacity; 774,387 Dths

·         STA 245 (Segment 245 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 740,766 Dths

·         STA 249 (Segment 249 FH) - through approx 67% of SOP due to nominations in excess of operational capacity; 376,216 Dths

·         MLV 273 (Segment 284 FH) - through approx 74% of SOP due to nominations in excess of operational capacity; 150,700 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  03/27/2025 3:46:47PM Notice End Date/Time:  03/28/2025 9:00:00am
Post Date/Time:  3/27/2025 3:46:47 PM Notice ID: 394152
Reqrd Rsp:  1 Rsp Date:  03/27/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 03-28-2025 TC REVISED
Notice Text:

Effective Timely Cycle (9:00) for the gas day of Friday, March 28, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

REVISED

 

METER RESTRICTIONS

·         Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 80,000 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP due to operational concerns; 5,000 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths

·         Atmos KY/TGP Danville Ky Boyle Delivery Meter (Pin 400462) - through approx 3% of SOP due to nominations in excess of operational capacity; 245 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 59% of SIPss due to nominations in excess of operational capacity; 64,863 Dths

SEGMENT RESTRICTIONS

·         STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to emergent repair at STA 40; 10,664 Dths

·         STA 823 (Segment 823 BH) - through 100% of SOP due to nominations in excess of operational capacity; 25,182 Dths

·         STA 834 (Segment 834 BH) - through approx 48% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 70,047 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 69,826 Dths

·         STA 307 (Segment 307 BH) - through approx 84% of SOP due to nominations in excess of operational capacity; 223,563 Dths

·         MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 275,788 Dths

·         STA 315 (Segment 315 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 456,028 Dths

·         STA 321 (Segment 321 FH) - through approx 45% of SOP due to emergent repair at STA 321 UNIT 5B; 370,111 Dths

·         MLV 330 (Segment 324 FH) - through approx 22% of SOP due to nominations in excess of operational capacity; 95,823 Dths

·         MLV 336 East (Segment 336 FH) - through approx 97% of SOP due to nominations in excess of operational capacity; 83,833 Dths

·         Z5hc North (Segment 299 FH) - through approx 90% of SOP due to nominations in excess of operational capacity; 774,387 Dths

·         STA 245 (Segment 245 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 740,766 Dths

·         STA 249 (Segment 249 FH) - through approx 67% of SOP due to nominations in excess of operational capacity; 376,216 Dths

·         MLV 273 (Segment 284 FH) - through approx 74% of SOP due to nominations in excess of operational capacity; 150,700 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.