Tennessee Gas Pipeline Notice 394221

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/04/2025 10:56:56AM Notice End Date/Time:  04/05/2025 9:00:00am
Post Date/Time:  4/4/2025 10:56:56 AM Notice ID: 394221
Reqrd Rsp:  1 Rsp Date:  04/04/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-04-2025 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Friday, April 04, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

 

 

METER RESTRICTIONS

·         LASERGTH/TGP Riverside Wilson 1 Nu Receipt Meter (Pin 412124) - through approx 19 % of SA increases due to nominations in excess of operational capacity; 1,917 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 100 % of SOP increases due to operational concerns; 11,149 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 96 % of SIPss increases due to nominations in excess of operational capacity; 66,798 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 6,896 Dths

·         STA 860 (Segment 860 BH) - through approx 100 % of PIP increases due to force majeure at STA 860; 6,000 Dths

·         STA 307 (Segment 307 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 433,714 Dths

·         MLV 314 East (Segment 314 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 283,011 Dths

·         STA 315 (Segment 315 BH) - through approx 95 % of SOP increases due to nominations in excess of operational capacity; 433,528 Dths

·         STA 321 (Segment 321 FH) - through approx 30 % of SOP increases due to emergent repair at STA 321 UNIT 5B; 49,792 Dths

·         MLV 330 (Segment 324 FH) - through approx 43 % of SOP increases due to nominations in excess of operational capacity; 40,909 Dths

·         Z5hc North (Segment 299 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 320,230 Dths

·         STA 245 (Segment 245 FH) - through approx 98 % of SOP increases due to nominations in excess of operational capacity; 395,793 Dths

·         STA 249 (Segment 249 FH) - through approx 96 % of SOP increases due to nominations in excess of operational capacity; 221,785 Dths

·         MLV 273 (Segment 284 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 222,389 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/04/2025 10:56:56AM Notice End Date/Time:  04/05/2025 9:00:00am
Post Date/Time:  4/4/2025 10:56:56 AM Notice ID: 394221
Reqrd Rsp:  1 Rsp Date:  04/04/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-04-2025 ID1
Notice Text:

Effective Intraday 1 Cycle (14:00) for the gas day of Friday, April 04, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

 

 

METER RESTRICTIONS

·         LASERGTH/TGP Riverside Wilson 1 Nu Receipt Meter (Pin 412124) - through approx 19 % of SA increases due to nominations in excess of operational capacity; 1,917 Dths

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 100 % of SOP increases due to operational concerns; 11,149 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 96 % of SIPss increases due to nominations in excess of operational capacity; 66,798 Dths

SEGMENT RESTRICTIONS

·         STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 6,896 Dths

·         STA 860 (Segment 860 BH) - through approx 100 % of PIP increases due to force majeure at STA 860; 6,000 Dths

·         STA 307 (Segment 307 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 433,714 Dths

·         MLV 314 East (Segment 314 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 283,011 Dths

·         STA 315 (Segment 315 BH) - through approx 95 % of SOP increases due to nominations in excess of operational capacity; 433,528 Dths

·         STA 321 (Segment 321 FH) - through approx 30 % of SOP increases due to emergent repair at STA 321 UNIT 5B; 49,792 Dths

·         MLV 330 (Segment 324 FH) - through approx 43 % of SOP increases due to nominations in excess of operational capacity; 40,909 Dths

·         Z5hc North (Segment 299 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 320,230 Dths

·         STA 245 (Segment 245 FH) - through approx 98 % of SOP increases due to nominations in excess of operational capacity; 395,793 Dths

·         STA 249 (Segment 249 FH) - through approx 96 % of SOP increases due to nominations in excess of operational capacity; 221,785 Dths

·         MLV 273 (Segment 284 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 222,389 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.