TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/11/2025 3:24:12PM Notice End Date/Time:  04/12/2025 9:00:00am
Post Date/Time:  4/11/2025 3:24:12 PM Notice ID: 394285
Reqrd Rsp:  1 Rsp Date:  04/11/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-11-2025 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of Friday, April 11, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

 

 

METER RESTRICTIONS

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 8,000 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of PIP increases due to operational concerns; 1,177 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 94% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 37,233 Dths

·         STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,000 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 418,714 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 305,868 Dths

·         STA 315 (Segment 315 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 188,368 Dths

·         STA 321 (Segment 321 FH) - through approx 69% of SOP increases due to emergent repair at STA 321 UNIT 5B; 122,764 Dths

·         MLV 330 (Segment 324 FH) - through approx 36% of SOP increases due to nominations in excess of operational capacity; 17,690 Dths

·         Z5hc North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 319,997 Dths

·         STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 458,831 Dths

·         STA 249 (Segment 249 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 304,016 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 115,557 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 170,018 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  04/11/2025 3:24:12PM Notice End Date/Time:  04/12/2025 9:00:00am
Post Date/Time:  4/11/2025 3:24:12 PM Notice ID: 394285
Reqrd Rsp:  1 Rsp Date:  04/11/2025
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 04-11-2025 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of Friday, April 11, 2025 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

NONE

 

 

 

METER RESTRICTIONS

·         Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 8,000 Dths

·         TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of PIP increases due to operational concerns; 1,177 Dths

SEGMENT RESTRICTIONS

·         STA 25 (Segment 125 FH) - through approx 94% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 37,233 Dths

·         STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,000 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 418,714 Dths

·         MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 305,868 Dths

·         STA 315 (Segment 315 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 188,368 Dths

·         STA 321 (Segment 321 FH) - through approx 69% of SOP increases due to emergent repair at STA 321 UNIT 5B; 122,764 Dths

·         MLV 330 (Segment 324 FH) - through approx 36% of SOP increases due to nominations in excess of operational capacity; 17,690 Dths

·         Z5hc North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 319,997 Dths

·         STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 458,831 Dths

·         STA 249 (Segment 249 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 304,016 Dths

·         STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 115,557 Dths

·         MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 170,018 Dths

LINEPACK RESTRICTIONS

Payback will be evaluated at each cycle and scheduled only if operationally feasible.

 

 

 

STORAGE RESTRICTIONS

NONE

 

 

 

**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.

**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.