Tennessee Gas Pipeline Notice 394321
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 04/16/2025 3:49:06PM | Notice End Date/Time: 04/17/2025 9:00:00am |
Post Date/Time: 4/16/2025 3:49:06 PM | Notice ID: 394321 |
Reqrd Rsp: 1 | Rsp Date: 04/16/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 04-16-2025 ID2 |
Effective Intraday 2 Cycle (18:00) for the gas day of Wednesday, April 16, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 70,000 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 5,000 Dths
· TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of PIP increases due to operational concerns; 899 Dths
SEGMENT RESTRICTIONS
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,173 Dths
· STA 307 (Segment 307 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 324,841 Dths
· MLV 314 East (Segment 314 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 264,327 Dths
· STA 315 (Segment 315 BH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 176,618 Dths
· STA 321 (Segment 321 FH) - through approx 84% of SOP increases due to nominations in excess of operational capacity and due to emergent repair at STA 321 UNIT 5B; 202,914 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 364,234 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 454,282 Dths
· STA 249 (Segment 249 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 285,750 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 31% of SOP increases due to nominations in excess of operational capacity; 12,904 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 175,348 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
TSP/TSP Name: 1939164-TENNESSEE GAS PIPELINE | Critical: Y |
Notice Type Desc (1): PIPELINE CONDITIONS | Notice Type Desc (2): CURRENT PIPELINE CONDITIONS |
Notice Eff Date/Time: 04/16/2025 3:49:06PM | Notice End Date/Time: 04/17/2025 9:00:00am |
Post Date/Time: 4/16/2025 3:49:06 PM | Notice ID: 394321 |
Reqrd Rsp: 1 | Rsp Date: 04/16/2025 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: RESTRICTIONS FOR 04-16-2025 ID2 |
Effective Intraday 2 Cycle (18:00) for the gas day of Wednesday, April 16, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 70,000 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 5,000 Dths
· TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of PIP increases due to operational concerns; 899 Dths
SEGMENT RESTRICTIONS
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,173 Dths
· STA 307 (Segment 307 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 324,841 Dths
· MLV 314 East (Segment 314 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 264,327 Dths
· STA 315 (Segment 315 BH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 176,618 Dths
· STA 321 (Segment 321 FH) - through approx 84% of SOP increases due to nominations in excess of operational capacity and due to emergent repair at STA 321 UNIT 5B; 202,914 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 364,234 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 454,282 Dths
· STA 249 (Segment 249 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 285,750 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 31% of SOP increases due to nominations in excess of operational capacity; 12,904 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 175,348 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.