TransColorado Gas Transmission Notice 121886
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 938939154-TRANSCOLORADO GAS TRANS CO LLC | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 07/30/2024 8:04:54AM | Notice End Date/Time: 07/31/2024 9:00:00am |
Post Date/Time: 7/30/2024 8:04:54 AM | Notice ID: 121886 |
Reqrd Rsp: 1 | Rsp Date: 07/30/2024 |
Notice Stat Desc: SUPERSEDE | Prior Notice: 121824 |
Subject: Operation Planning Report V3 July 2024 |
TransColorado Pipeline Company Reissued July 30, 2024 |
Deletion:
OLATHE C.S. TO RED VALE C.S. (Segment 230): TransColorado cancels the pigging operations Racoon Hollow to Olathe Compressor Station July 31.
2 |
OLATHE C.S. TO RED VALE C.S. (Segment 230): TransColorado will be performing pigging operations Racoon Hollow to Olathe Compressor Station July 12 and July 31. This outage results in the following impacts. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 12 |
230 |
260 |
0 |
|
July 31 |
230 |
260 |
0 |
|
TD1 Southbound |
|
|
|
|
July 12 |
364 |
364 |
170 |
|
July 31 |
364 |
364 |
170 |
JULY 2024 |
||||||||||||||||||||||||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
|
|
|
|
|
|
|
|
1 |
1 |
|
2 |
|
|
|
|
|
|
|
|
|
|
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
4 |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE
1 |
DOLORES C.S. TO MANCOS C.S. (Segment 250): Mancos Compressor Station, TransColorado, will be performing Station DOT/ESD test July 9 through July 10. This outage results in the following impacts. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 9 |
250 |
260 |
220 |
|
July 10 |
250 |
260 |
238 |
|
TD1 Southbound |
||||
July 9 |
250 |
361 |
311 |
|
July 10 |
250 |
361 |
334 |
3 |
BLANCO COMPRESSOR (Segment 310): Blanco Compressor Station, TransColorado, will be performing Station DOT/ESD test July 23. This outage results in the following impacts. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 23 Cycles 1 thru 4 |
310 |
260 |
178 |
|
July 23 Cycle 5 |
310 |
260 |
215** |
|
** The nomination limit for this cycle has been prorated for the remaining time in the gas day |
4 |
BLANCO COMPRESSOR (Segment 310): Blanco Compressor Station, TransColorado, will be performing unit repair July 9 through July 11. This outage results in the following impact. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 9 thru July 11 |
310 |
260 |
178 |
Any comments or questions about this report should be directed to Vic Villalva at (719) 520-4251 or Cheryl Bauer at (719) 520-4423.
TSP/TSP Name: 938939154-TRANSCOLORADO GAS TRANS CO LLC | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 07/30/2024 8:04:54AM | Notice End Date/Time: 07/31/2024 9:00:00am |
Post Date/Time: 7/30/2024 8:04:54 AM | Notice ID: 121886 |
Reqrd Rsp: 1 | Rsp Date: 07/30/2024 |
Notice Stat Desc: SUPERSEDE | Prior Notice: 121824 |
Subject: Operation Planning Report V3 July 2024 |
TransColorado Pipeline Company Reissued July 30, 2024 |
Deletion:
OLATHE C.S. TO RED VALE C.S. (Segment 230): TransColorado cancels the pigging operations Racoon Hollow to Olathe Compressor Station July 31.
2 |
OLATHE C.S. TO RED VALE C.S. (Segment 230): TransColorado will be performing pigging operations Racoon Hollow to Olathe Compressor Station July 12 and July 31. This outage results in the following impacts. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 12 |
230 |
260 |
0 |
|
July 31 |
230 |
260 |
0 |
|
TD1 Southbound |
|
|
|
|
July 12 |
364 |
364 |
170 |
|
July 31 |
364 |
364 |
170 |
JULY 2024 |
||||||||||||||||||||||||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
|
|
|
|
|
|
|
|
1 |
1 |
|
2 |
|
|
|
|
|
|
|
|
|
|
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4 |
4 |
4 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TRANSCOLORADO GAS PIPELINE COMPANY MAINTENANCE
1 |
DOLORES C.S. TO MANCOS C.S. (Segment 250): Mancos Compressor Station, TransColorado, will be performing Station DOT/ESD test July 9 through July 10. This outage results in the following impacts. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 9 |
250 |
260 |
220 |
|
July 10 |
250 |
260 |
238 |
|
TD1 Southbound |
||||
July 9 |
250 |
361 |
311 |
|
July 10 |
250 |
361 |
334 |
3 |
BLANCO COMPRESSOR (Segment 310): Blanco Compressor Station, TransColorado, will be performing Station DOT/ESD test July 23. This outage results in the following impacts. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 23 Cycles 1 thru 4 |
310 |
260 |
178 |
|
July 23 Cycle 5 |
310 |
260 |
215** |
|
** The nomination limit for this cycle has been prorated for the remaining time in the gas day |
4 |
BLANCO COMPRESSOR (Segment 310): Blanco Compressor Station, TransColorado, will be performing unit repair July 9 through July 11. This outage results in the following impact. |
|||
Dates |
Segment |
Operating Capacity (MDth/d) |
Reduced to Capacity (MDth/d) |
|
TD2 Northbound |
||||
July 9 thru July 11 |
310 |
260 |
178 |
Any comments or questions about this report should be directed to Vic Villalva at (719) 520-4251 or Cheryl Bauer at (719) 520-4423.