TransCanada Canadian Mainline Notice 3374723621
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
Capacity Constraint
Effective Start Date Time
02/20/2025 8:12 pm
Subject
Eastern Triangle Pipeline System Maintenance Feb 24 - Feb 27
Notice Text
TC Energy provides notice that the upcoming in-line inspections on the NPS 24 Montreal Line in the Eastern Triangle announced to begin on February 24 are commencing as planned.
EDA capacity is expected to be approximately 3460 TJ for the maintenance period from February 24 to February 27.
Depending on demand levels, discretionary services may be limited past the Union/Enbridge/KPUC/Napanee EDAs to downstream locations i.e. Iroquois and East Hereford.
Firm services to the Eastern Delivery Area (EDA) and downstream export points are not anticipated to be impacted.
Dates are subject to change and will be communicated as required.
QUESTIONS
If you have any questions or require further information, please contact your Marketing Representative
Capacity Constraint
Effective Start Date Time
02/20/2025 8:12 pm
Subject
Eastern Triangle Pipeline System Maintenance Feb 24 - Feb 27
Notice Text
TC Energy provides notice that the upcoming in-line inspections on the NPS 24 Montreal Line in the Eastern Triangle announced to begin on February 24 are commencing as planned.
EDA capacity is expected to be approximately 3460 TJ for the maintenance period from February 24 to February 27.
Depending on demand levels, discretionary services may be limited past the Union/Enbridge/KPUC/Napanee EDAs to downstream locations i.e. Iroquois and East Hereford.
Firm services to the Eastern Delivery Area (EDA) and downstream export points are not anticipated to be impacted.
Dates are subject to change and will be communicated as required.