Trunkline Gas Notice 38917

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice ID: 38917
Notice Type: MAI
Critical: Y
Notice Status Description:
Reqrd Rsp Desc:
Posting Date/Time: 2023-09-14 08:09:00.0
Subject: TGC Piping Modifications
Notice Effective Date/Time: 2023-09-14 08:09:00.0
Notice End Date/Time: 2200-01-01 00:00:00.0
Notice Text:

09/14/2023  TGC Piping Modifications

Beginning Gas Day September 27, 2023, Trunkline has scheduled planned maintenance for piping modifications on the 300-1 Line at Milepost -81.62 in Louisiana.  The impact of this work will be defined by the timeframes outlined below:

 

1st Phase

9/27/2023 to 10/2/2023

2nd  Phase

10/3/2023 to 10/4/2023

 

 

During the first phase, operators could experience pressure fluctuations. Scheduling reductions may occur to reduce imbalances and maintain the safety and integrity of operations on the pipe.

 

During the second phase, all backhaul and forward haul nominations that traverse across the East and West Louisiana segment boundary must net to zero and are subject to scheduling reductions. 

 

If the scheduling reductions impact firm shippers, the Reservation Charge Crediting Mechanism of Section 29.1 (A) (2) shall apply.

Updates to this maintenance will be posted as they become available.

 

If you have any questions, please contact your Customer Service or Marketing Representative.

 

 

 

 

 

Notice ID: 38917
Notice Type: MAI
Critical: Y
Notice Status Description:
Reqrd Rsp Desc:
Posting Date/Time: 2023-09-14 08:09:00.0
Subject: TGC Piping Modifications
Notice Effective Date/Time: 2023-09-14 08:09:00.0
Notice End Date/Time: 2200-01-01 00:00:00.0
Notice Text:

09/14/2023  TGC Piping Modifications

Beginning Gas Day September 27, 2023, Trunkline has scheduled planned maintenance for piping modifications on the 300-1 Line at Milepost -81.62 in Louisiana.  The impact of this work will be defined by the timeframes outlined below:

 

1st Phase

9/27/2023 to 10/2/2023

2nd  Phase

10/3/2023 to 10/4/2023

 

 

During the first phase, operators could experience pressure fluctuations. Scheduling reductions may occur to reduce imbalances and maintain the safety and integrity of operations on the pipe.

 

During the second phase, all backhaul and forward haul nominations that traverse across the East and West Louisiana segment boundary must net to zero and are subject to scheduling reductions. 

 

If the scheduling reductions impact firm shippers, the Reservation Charge Crediting Mechanism of Section 29.1 (A) (2) shall apply.

Updates to this maintenance will be posted as they become available.

 

If you have any questions, please contact your Customer Service or Marketing Representative.