USG Pipeline Company, LLC: Operational Flow Order
Critical Notice Description:
Operational Flow Order
Notice Effective Date:
8/4/2014
Notice Effective Time:
7:00 AM CST
Notice End Date:
8/5/2014
Notice End Time:
12:00 AM CST
Notice Type:
Capacity Constraint
Subject:
USG Pipeline Company, LLC DOT Pipeline Maintenance
Notice Text:
As part of its DOT Pipeline Integrity Project, USG Pipeline Company, LLC (USGPC) will be conducting
pigging operations on its 10” Main Line.
Integrity Project:
ILI Tool Date: 8/4/2014
During the tool run, both Firm and Interruptible services will be restricted pursuant to Section 8 of USG
Pipeline’s tariff.
Restrictions are as follows:
Starting at 7:00 AM CST on 8/4/2014 and continuing through 12:00 AM CST on 8/5/2014 total flows will
be restricted to 0 (zero) for all customers.
Based on the results of the ILI Tool, additional runs may be required which could extend the pipeline
restrictions. USGPC will post updates as soon as it is known.
Please call or email your operations account manager should you have any questions or concerns.
Critical Notice Description:
Operational Flow Order
Notice Effective Date:
8/4/2014
Notice Effective Time:
7:00 AM CST
Notice End Date:
8/5/2014
Notice End Time:
12:00 AM CST
Notice Type:
Capacity Constraint
Subject:
USG Pipeline Company, LLC DOT Pipeline Maintenance
Notice Text:
As part of its DOT Pipeline Integrity Project, USG Pipeline Company, LLC (USGPC) will be conducting
pigging operations on its 10” Main Line.
Integrity Project:
ILI Tool Date: 8/4/2014
During the tool run, both Firm and Interruptible services will be restricted pursuant to Section 8 of USG
Pipeline’s tariff.
Restrictions are as follows:
Starting at 7:00 AM CST on 8/4/2014 and continuing through 12:00 AM CST on 8/5/2014 total flows will
be restricted to 0 (zero) for all customers.
Based on the results of the ILI Tool, additional runs may be required which could extend the pipeline
restrictions. USGPC will post updates as soon as it is known.
Please call or email your operations account manager should you have any questions or concerns.