Viking Gas Transmission Company Notice 3050
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Viking Gas Transmission Company
TSP: 60-916-6673
Subject: COMPLETE: FORCE MAJEURE: Unplanned Capacity Constraint - Flow South of Angus CS #2204
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 09/02/2024 12:37 pm
Notice Eff Date/Time: 08/29/2024 06:51 pm
NOTICE_END_DATE: 09/02/2024 06:00 pm
Notice ID: 3050
Notice Stat Desc: Supersede
Prior Notice: 3048
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 is complete.
The Flow South of Angus CS #2204 capacity has been increased to 564,700 Dth effective Gas Day, September 2, 2024, Intra-Day 2 Cycle.
Please contact your Commercial Representative with any further questions.
----------------------------------------
Prior Notice ID: 3049
On Notice ID #3048, Viking Gas Transmission Company (VGT) posted notice of unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 anticipated to be in effect through September 6, 2024. VGT has evaluated the circumstances of this outage and has determined this event qualifies as a Force Majeure event per Part 8, Section 10 of its tariff.
VGT is working to restore Flow South of Angus Compressor Station (CS) #2204 to full service. VGT Gas Control will continue to monitor pipeline conditions and will update this outage as operational conditions change.
Please contact your Commercial representative with any further questions.
------------------------------------------
Prior Notice ID: 3048
Due to an unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease Flow South of Angus CS #2204 capacity beginning Gas Day, August 29, 2024, Intra-Day 3 (ID3) Cycle. This capacity constraint is anticipated to be in effect through Gas Day, September 6, 2024.
Flow South of Angus CS #2204 capacity will be reduced from 564,700 Dth to 316,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
Please contact your Commercial representative with questions.
TSP: 60-916-6673
Subject: COMPLETE: FORCE MAJEURE: Unplanned Capacity Constraint - Flow South of Angus CS #2204
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 09/02/2024 12:37 pm
Notice Eff Date/Time: 08/29/2024 06:51 pm
NOTICE_END_DATE: 09/02/2024 06:00 pm
Notice ID: 3050
Notice Stat Desc: Supersede
Prior Notice: 3048
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 is complete.
The Flow South of Angus CS #2204 capacity has been increased to 564,700 Dth effective Gas Day, September 2, 2024, Intra-Day 2 Cycle.
Please contact your Commercial Representative with any further questions.
----------------------------------------
Prior Notice ID: 3049
On Notice ID #3048, Viking Gas Transmission Company (VGT) posted notice of unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 anticipated to be in effect through September 6, 2024. VGT has evaluated the circumstances of this outage and has determined this event qualifies as a Force Majeure event per Part 8, Section 10 of its tariff.
VGT is working to restore Flow South of Angus Compressor Station (CS) #2204 to full service. VGT Gas Control will continue to monitor pipeline conditions and will update this outage as operational conditions change.
Please contact your Commercial representative with any further questions.
------------------------------------------
Prior Notice ID: 3048
Due to an unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease Flow South of Angus CS #2204 capacity beginning Gas Day, August 29, 2024, Intra-Day 3 (ID3) Cycle. This capacity constraint is anticipated to be in effect through Gas Day, September 6, 2024.
Flow South of Angus CS #2204 capacity will be reduced from 564,700 Dth to 316,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
Please contact your Commercial representative with questions.
TSP Name: Viking Gas Transmission Company
TSP: 60-916-6673
Subject: COMPLETE: FORCE MAJEURE: Unplanned Capacity Constraint - Flow South of Angus CS #2204
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 09/02/2024 12:37 pm
Notice Eff Date/Time: 08/29/2024 06:51 pm
NOTICE_END_DATE: 09/02/2024 06:00 pm
Notice ID: 3050
Notice Stat Desc: Supersede
Prior Notice: 3048
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 is complete.
The Flow South of Angus CS #2204 capacity has been increased to 564,700 Dth effective Gas Day, September 2, 2024, Intra-Day 2 Cycle.
Please contact your Commercial Representative with any further questions.
----------------------------------------
Prior Notice ID: 3049
On Notice ID #3048, Viking Gas Transmission Company (VGT) posted notice of unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 anticipated to be in effect through September 6, 2024. VGT has evaluated the circumstances of this outage and has determined this event qualifies as a Force Majeure event per Part 8, Section 10 of its tariff.
VGT is working to restore Flow South of Angus Compressor Station (CS) #2204 to full service. VGT Gas Control will continue to monitor pipeline conditions and will update this outage as operational conditions change.
Please contact your Commercial representative with any further questions.
------------------------------------------
Prior Notice ID: 3048
Due to an unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease Flow South of Angus CS #2204 capacity beginning Gas Day, August 29, 2024, Intra-Day 3 (ID3) Cycle. This capacity constraint is anticipated to be in effect through Gas Day, September 6, 2024.
Flow South of Angus CS #2204 capacity will be reduced from 564,700 Dth to 316,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
Please contact your Commercial representative with questions.
TSP: 60-916-6673
Subject: COMPLETE: FORCE MAJEURE: Unplanned Capacity Constraint - Flow South of Angus CS #2204
Notice Type: Constraint
Critical: Yes
Post Date/Time:: 09/02/2024 12:37 pm
Notice Eff Date/Time: 08/29/2024 06:51 pm
NOTICE_END_DATE: 09/02/2024 06:00 pm
Notice ID: 3050
Notice Stat Desc: Supersede
Prior Notice: 3048
Reqrd Rsp Desc: No response required
Rsp Date/Time:
Notice Text:
The unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 is complete.
The Flow South of Angus CS #2204 capacity has been increased to 564,700 Dth effective Gas Day, September 2, 2024, Intra-Day 2 Cycle.
Please contact your Commercial Representative with any further questions.
----------------------------------------
Prior Notice ID: 3049
On Notice ID #3048, Viking Gas Transmission Company (VGT) posted notice of unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204 anticipated to be in effect through September 6, 2024. VGT has evaluated the circumstances of this outage and has determined this event qualifies as a Force Majeure event per Part 8, Section 10 of its tariff.
VGT is working to restore Flow South of Angus Compressor Station (CS) #2204 to full service. VGT Gas Control will continue to monitor pipeline conditions and will update this outage as operational conditions change.
Please contact your Commercial representative with any further questions.
------------------------------------------
Prior Notice ID: 3048
Due to an unplanned maintenance at the Flow South of Angus Compressor Station (CS) #2204, Viking Gas Transmission Company (VGT) will decrease Flow South of Angus CS #2204 capacity beginning Gas Day, August 29, 2024, Intra-Day 3 (ID3) Cycle. This capacity constraint is anticipated to be in effect through Gas Day, September 6, 2024.
Flow South of Angus CS #2204 capacity will be reduced from 564,700 Dth to 316,000 Dth.
VGT does anticipate an impact to firm transportation service. Reservation charge credits will be applied pursuant to VGT's FERC Gas Tariff, General Terms and Conditions, Section 34.
Please contact your Commercial representative with questions.