Empire Pipeline Notice 1133088
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP Name: Empire Pipeline, Inc. - Critical Notice
TSP: 609775049
Post Date: 1/13/2025
Post Time: 10:37:00AM CCT
Notice Type: Curtailment, Planned Service Outage, Scheduling Alert
Reqrd Rsp: 5
Critical: Y
Notice ID: 1133088
Notice Status: 2
Notice Eff Date/Time: 4/22/2025 09:00:00AM CCT
Notice End Date/Time: 5/3/2025 09:00:00AM CCT
Superseded System Notice ID: 1127823
Subject: Jackson Station Outages: April 2025 - Revision 1
Notice Text
Jackson Station Outages: April 2025 - Revision 1
Outages at Jackson compressor have been moved from March to April 2025, and outage dates have been finalized:
Total station outage: 4/22/2025 (GD22) through 4/23/2025 (GD23) - Estimated 40-45% curtailment of primary receipts
from Tuscarora (022009010), NFG Midstream Covington (EPRU91111), Repsol Oil & Gas (EPRU91101), and Corning (022008810).
Single unit outage – 4/24/2025 (GD24) through 5/3/2025 (GD3) : No curtailment expected at this time.
Empire Pipeline will work with upstream operators to limit the impact of these outages to shippers.
Updates will be provided as they become available.
********** Prior Notice Below **********
Jackson Station Outages – March 2025
Jackson compressor station will require the following outages in March 2025:
Total station outage – 2 days: Estimated 40-45% curtailment of primary receipts from Tuscarora (022009010), NFG Midstream Covington (EPRU91111),
Repsol Oil & Gas (EPRU91101), and Corning (022008810).
Single unit outage – up to 10 days: No curtailment expected at this time.
These outages will occur consecutively and in the order listed. Empire Pipeline will work with upstream operators to limit the
impact of these outages to shippers.
Updates, including specific outage dates, will be provided as they become available.
TSP Name: Empire Pipeline, Inc. - Critical Notice
TSP: 609775049
Post Date: 1/13/2025
Post Time: 10:37:00AM CCT
Notice Type: Curtailment, Planned Service Outage, Scheduling Alert
Reqrd Rsp: 5
Critical: Y
Notice ID: 1133088
Notice Status: 2
Notice Eff Date/Time: 4/22/2025 09:00:00AM CCT
Notice End Date/Time: 5/3/2025 09:00:00AM CCT
Superseded System Notice ID: 1127823
Subject: Jackson Station Outages: April 2025 - Revision 1
Notice Text
Jackson Station Outages: April 2025 - Revision 1
Outages at Jackson compressor have been moved from March to April 2025, and outage dates have been finalized:
Total station outage: 4/22/2025 (GD22) through 4/23/2025 (GD23) - Estimated 40-45% curtailment of primary receipts
from Tuscarora (022009010), NFG Midstream Covington (EPRU91111), Repsol Oil & Gas (EPRU91101), and Corning (022008810).
Single unit outage – 4/24/2025 (GD24) through 5/3/2025 (GD3) : No curtailment expected at this time.
Empire Pipeline will work with upstream operators to limit the impact of these outages to shippers.
Updates will be provided as they become available.
********** Prior Notice Below **********
Jackson Station Outages – March 2025
Jackson compressor station will require the following outages in March 2025:
Total station outage – 2 days: Estimated 40-45% curtailment of primary receipts from Tuscarora (022009010), NFG Midstream Covington (EPRU91111),
Repsol Oil & Gas (EPRU91101), and Corning (022008810).
Single unit outage – up to 10 days: No curtailment expected at this time.
These outages will occur consecutively and in the order listed. Empire Pipeline will work with upstream operators to limit the
impact of these outages to shippers.
Updates, including specific outage dates, will be provided as they become available.