Empire Pipeline Notice 1149361

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP Name: Empire Pipeline, Inc. - Critical Notice

TSP: 609775049

                                                                                                                        Post Date: 3/18/2025
                                                                                                                        Post Time: 02:33:00PM CCT
Notice Type: Maintenance, Scheduling Alert
                                                                                                                        Reqrd Rsp: 5
Critical: Y
Notice ID: 1149361
Notice Status: 2
Notice Eff Date/Time: 5/14/2025 06:00:00AM CCT
Notice End Date/Time: 5/17/2025 09:00:00AM CCT
Superseded System Notice ID: 1146560

Subject: Mendon to Chippawa Cleaning & ILI: May 2025 - Revision 1
Notice Text
Mendon to Chippawa Cleaning & ILI: May 2025 - Revision 1

Specific outage dates have been added and pigging rates updated:

The Empire West mainline will undergo cleaning on 5/14 and inline inspection (ILI) on 5/16.
The following flow rates through Oakfield (East to West) are required for pigging:

Cleaning (5/14): 235,000 dth

ILI (5/16): 300,000 dth

Given recent scheduling history, no impact to shippers is currently expected. However, this is
subject to change and will be re-evaluated at a later date.

Updates will be provided as available.


********** Prior Notice Below **********

Mendon to Chippawa Cleaning & ILI – May 2025

The Empire West mainline will undergo cleaning and inline inspection (ILI) in early May 2025.
The following flow rates through Oakfield (East to West) are required for pigging:

Cleaning (1 Gas Day): 180,000 dth

ILI (1 Gas Day): 230,000 dth

Given recent scheduling history, no impact to shippers is currently expected. However, this is
subject to change and will be re-evaluated at a later date.

Updates, including refined outage dates and shipper impact will be provided as they become available.

TSP Name: Empire Pipeline, Inc. - Critical Notice

TSP: 609775049

Post Date: 3/18/2025
Post Time: 02:33:00PM CCT
Notice Type: Maintenance, Scheduling Alert
Reqrd Rsp: 5
Critical: Y
Notice ID: 1149361
Notice Status: 2
Notice Eff Date/Time: 5/14/2025 06:00:00AM CCT
Notice End Date/Time: 5/17/2025 09:00:00AM CCT
Superseded System Notice ID: 1146560

Subject: Mendon to Chippawa Cleaning & ILI: May 2025 - Revision 1
Notice Text
Mendon to Chippawa Cleaning & ILI: May 2025 - Revision 1

Specific outage dates have been added and pigging rates updated:

The Empire West mainline will undergo cleaning on 5/14 and inline inspection (ILI) on 5/16.
The following flow rates through Oakfield (East to West) are required for pigging:

Cleaning (5/14): 235,000 dth

ILI (5/16): 300,000 dth

Given recent scheduling history, no impact to shippers is currently expected. However, this is
subject to change and will be re-evaluated at a later date.

Updates will be provided as available.


********** Prior Notice Below **********

Mendon to Chippawa Cleaning & ILI – May 2025

The Empire West mainline will undergo cleaning and inline inspection (ILI) in early May 2025.
The following flow rates through Oakfield (East to West) are required for pigging:

Cleaning (1 Gas Day): 180,000 dth

ILI (1 Gas Day): 230,000 dth

Given recent scheduling history, no impact to shippers is currently expected. However, this is
subject to change and will be re-evaluated at a later date.

Updates, including refined outage dates and shipper impact will be provided as they become available.