Florida Gas Transmission Notice 49706

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

Notice ID: 49706
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Nov 26 2024 9:07AM
Subject: December 2024 --- FGT SUPPLY AREA MAINTENANCE IN Zone 3 - Second Update
Notice Effective Date/Time: Dec 1 2024 8:52AM
Notice End Date/Time: Dec 31 2024 9:00AM
Notice Text:

FGT will be performing pipeline maintenance near FGT Compressor Station 10. This maintenance will begin December 1, 2024, and is to be completed by the end of gas day on December 14, 2024. During this maintenance, FGT may schedule up to 1,200,000 MMBtu/day through Station 10. During normal operations, FGT schedules up to 1,300,000 MMBtu/day through Station 10.

FGT will be performing maintenance at FGT Compressor Station 11. This maintenance will begin December 5, 2024, and is to be completed by the end of gas day on December 11, 2024. During this maintenance, FGT may schedule up to 2,500,000 MMBtu/day. During normal operations, FGT schedules up to 3,250,000 MMBtu/day through Station 11.

FGT will be performing pipeline maintenance near FGT Compressor Station 12. This maintenance will begin December 1, 2024, and continue through December 31, 2024. During this maintenance, FGT may only be able to schedule up to 2,800,000 MMBtu/day range through FGT Compressor Station 12. During normal operations, FGT schedules up to 3,175,000 MMBtu/day through FGT Compressor Station 12.

Notice ID: 49706
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Nov 26 2024 9:07AM
Subject: December 2024 --- FGT SUPPLY AREA MAINTENANCE IN Zone 3 - Second Update
Notice Effective Date/Time: Dec 1 2024 8:52AM
Notice End Date/Time: Dec 31 2024 9:00AM
Notice Text:

FGT will be performing pipeline maintenance near FGT Compressor Station 10. This maintenance will begin December 1, 2024, and is to be completed by the end of gas day on December 14, 2024. During this maintenance, FGT may schedule up to 1,200,000 MMBtu/day through Station 10. During normal operations, FGT schedules up to 1,300,000 MMBtu/day through Station 10.

FGT will be performing maintenance at FGT Compressor Station 11. This maintenance will begin December 5, 2024, and is to be completed by the end of gas day on December 11, 2024. During this maintenance, FGT may schedule up to 2,500,000 MMBtu/day. During normal operations, FGT schedules up to 3,250,000 MMBtu/day through Station 11.

FGT will be performing pipeline maintenance near FGT Compressor Station 12. This maintenance will begin December 1, 2024, and continue through December 31, 2024. During this maintenance, FGT may only be able to schedule up to 2,800,000 MMBtu/day range through FGT Compressor Station 12. During normal operations, FGT schedules up to 3,175,000 MMBtu/day through FGT Compressor Station 12.