Natural Gas Pipeline Notice 45432
Source LinkAll information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.
TSP/TSP Name: 6931794-NATURAL GAS PIPELINE CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 09/26/2024 2:22:01PM | Notice End Date/Time: 10/31/2024 9:00:00am |
Post Date/Time: 9/26/2024 2:22:01 PM | Notice ID: 45432 |
Reqrd Rsp: 1 | Rsp Date: 09/26/2024 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: SEGMENT 25 - CS302 MAINTENANCE |
SEGMENT 25 – STATION MAINTENANCE - CS 302
As posted on Natural's Outage Impact Report (X24-1009439), Natural will be performing station maintenance at Compressor Station 302 (CS 302) located in Montgomery County, Texas (Segment 25 of Natural's Texok Zone). As a result, Natural is required to temporarily reduce the maximum operating capacity eastbound into Segment 25 from Segment 26 and Segment 22, thus limiting Natural's throughput capacity eastbound through CS 302 during this outage.
The scheduling constraint will be at CS 302; therefore, any gas received west of CS 302 for delivery east of CS 302 will be impacted for the duration of the outage. The Pooling Point - Texok Zone (LOC 10560) is located west of the constraint. Firm transportation associated with storage injections or withdrawals may be impacted.
As such, effective for gas day Tuesday, October 22, 2024, Timely Cycle, and continuing through gas day Friday, October 25, 2024, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 56% of contract MDQ through CS 302. Actual nomination levels and changes in pipeline conditions could result in changes to the percentages scheduled (lower or higher) on subsequent gas days. AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this outage.
Continue to monitor Natural's interactive website for any updates during this outage. Please contact your Account Director or Scheduling Representative if you have any questions.
TSP/TSP Name: 6931794-NATURAL GAS PIPELINE CO. | Critical: Y |
Notice Type Desc (1): MAINTENANCE | Notice Type Desc (2): MAINTENANCE |
Notice Eff Date/Time: 09/26/2024 2:22:01PM | Notice End Date/Time: 10/31/2024 9:00:00am |
Post Date/Time: 9/26/2024 2:22:01 PM | Notice ID: 45432 |
Reqrd Rsp: 1 | Rsp Date: 09/26/2024 |
Notice Stat Desc: INITIATE | Prior Notice: |
Subject: SEGMENT 25 - CS302 MAINTENANCE |
SEGMENT 25 – STATION MAINTENANCE - CS 302
As posted on Natural's Outage Impact Report (X24-1009439), Natural will be performing station maintenance at Compressor Station 302 (CS 302) located in Montgomery County, Texas (Segment 25 of Natural's Texok Zone). As a result, Natural is required to temporarily reduce the maximum operating capacity eastbound into Segment 25 from Segment 26 and Segment 22, thus limiting Natural's throughput capacity eastbound through CS 302 during this outage.
The scheduling constraint will be at CS 302; therefore, any gas received west of CS 302 for delivery east of CS 302 will be impacted for the duration of the outage. The Pooling Point - Texok Zone (LOC 10560) is located west of the constraint. Firm transportation associated with storage injections or withdrawals may be impacted.
As such, effective for gas day Tuesday, October 22, 2024, Timely Cycle, and continuing through gas day Friday, October 25, 2024, Natural will schedule Primary Firm and Secondary in-path Firm transports to no less than 56% of contract MDQ through CS 302. Actual nomination levels and changes in pipeline conditions could result in changes to the percentages scheduled (lower or higher) on subsequent gas days. AOR/ITS and Secondary out-of-path Firm transports will not be available for the duration of this outage.
Continue to monitor Natural's interactive website for any updates during this outage. Please contact your Account Director or Scheduling Representative if you have any questions.