Natural Gas Pipeline Notice 45559

Source Link

All information here is provided as a service and information is not guaranteed to be accurate. PipeRiv is not responsible for any incorrect information.

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  CAPACITY CONSTRAINT Notice Type Desc (2):  SEGMENTS
Notice Eff Date/Time:  11/06/2024 12:02:15PM Notice End Date/Time:  11/30/2024 9:00:00am
Post Date/Time:  11/6/2024 12:02:15 PM Notice ID: 45559
Reqrd Rsp:  1 Rsp Date:  11/06/2024
Notice Stat Desc:  TERMINATE Prior Notice:  45480
Subject:  SEGMENT 15 E. BRYAN PRIMARY ONLY LIFTED
Notice Text:

SEGMENT 15 - EAST BRYAN - PRIMARY ONLY

 

Effective for gas day Friday, November 8, 2024, Timely cycle and continuing thereafter, Natural has operating capacity available for eastbound flow through Segment 15 East Bryan in Natural's Texok Zone.  Therefore, the Primary only restriction has been lifted.  All transport services are available.

 

Please contact your Account Director or Scheduling Representative if you have any questions.

 

 

 

TSP/TSP Name:  6931794-NATURAL GAS PIPELINE CO. Critical: Y
Notice Type Desc (1):  CAPACITY CONSTRAINT Notice Type Desc (2):  SEGMENTS
Notice Eff Date/Time:  11/06/2024 12:02:15PM Notice End Date/Time:  11/30/2024 9:00:00am
Post Date/Time:  11/6/2024 12:02:15 PM Notice ID: 45559
Reqrd Rsp:  1 Rsp Date:  11/06/2024
Notice Stat Desc:  TERMINATE Prior Notice:  45480
Subject:  SEGMENT 15 E. BRYAN PRIMARY ONLY LIFTED
Notice Text:

SEGMENT 15 - EAST BRYAN - PRIMARY ONLY

 

Effective for gas day Friday, November 8, 2024, Timely cycle and continuing thereafter, Natural has operating capacity available for eastbound flow through Segment 15 East Bryan in Natural's Texok Zone.  Therefore, the Primary only restriction has been lifted.  All transport services are available.

 

Please contact your Account Director or Scheduling Representative if you have any questions.